Hiryuu Project Management

From Analytics Practicum
Revision as of 00:27, 8 January 2017 by Qianpin.lin.2013 (talk | contribs)
Jump to navigation Jump to search
Logo Hiryuu.png


Home

About Us

Project Overview

Findings

Project Management

Documentations

Overview Weekly Diary


Timeline

Tasks Start End Teammates Involved Status
Data Gathering and Scoping
Gather Data Week 0 Week 0 All Completed
Finalise Requirements with client Week 0 Week 0 All Completed
Scope Project Week 0 Week 0 All Completed
Research and Preparation
Explore software Week 0 Week 0 All Completed
Finalise Proposal Week 0 Week 0 All Completed
Create and update wiki page Week 0 Week 0 All Completed
Data Cleaning
Data collection Week 1 Week 2 All In Progress
Data cleaning and restructuring Week 1 Week 2 All In Progress
Resolve/remove incomplete data Week 1 Week 2 All In Progress
Data Modelling
Stage 1: Exploratory Analysis Week 3 Week 6 All Not Completed
Stage 2: Clustering Week 3 Week 6 All Not Completed
Stage 3: Time Series Analysis Week 3 Week 6 Jouta Not Completed
Stage 4: Geospatial Week 5 Week 10 Qianpin Not Completed
Interim Preparation
Gather feedback from Client Week 4 Week 8 All Not Completed
Prepare interim report and slides Week 6 Week 7 Jouta Not Completed
Application Building
Code the application Week 8 Week 11 All Not Completed
Testing the application Week 10 Week 12 All Not Completed
Gather feedback from Client Week 12 Week 16 All Not Completed
Iteration
Adjust analysis Week 12 Week 13 Jouta Not Completed
Refine results to improve clarity Week 12 Week 13 Wan Theng, Qianpin Not Completed
Final Preparation
Prepare Research Paper Week 14 Week 14 All Not Completed
Prepare Poster Week 15 Week 15 Qianpin Not Completed

Work Plan

  • Fortnightly meetings with Supervisor
  • Monthly meetings with Sponsor
Hiryuu Gantt Chart.JPG