Tasks Start End Teammates Involved Status
Requirements Gathering & Scoping
Confirm Project Topic Week 1 Week 1 All Completed
Gather Requirements from Client Week 1 Week 1 All Completed
Brainstorm Ideas for Analysis Week 1 Week 1 All Completed
Research & Preparation
Research on User Apps and Local Discount Websites Week 2 Week 2 All Completed
Explore Tools Week 2 Week 2 All Completed
Proposal
Create Proposal Week 3 Week 3 All Completed
Create Wiki Page Week 3 Week 3 All Completed
Data Cleaning
Data Collection Week 4 Week 4 Yi Sheng Completed
Data Cleaning Week 4 Week 8 All Completed
Modelling
Stage 1: Exploratory Analysis Week 4 Week 8 All Completed
Stage 2: Funnel Plot Analysis Week 7 Week 9 Elizabeth Completed
Stage 3: Time-Series Analysis Week 8 Week 10 Elizabeth & Kang Long Completed
Stage 4: Geospatial Analysis Week 7 Week 10 Yi Sheng Completed
Midterm Presentation
Create Midterm Report Week 7 Week 8 All Completed
Update Wiki Week 8 Week 8 Elizabeth Completed
Testing & Iteration
Stage 6: Refining and extrapolating Week 8 Week 13 All Completed
Meeting Client to get feedback Week 8 Week 13 All Completed
Refine Model based on feedback Week 8 Week 14 All Completed
Final Presentation
Prepare final presentation slides Week 14 Week 14 Kang Long & Yi Sheng Completed
Update Wiki Week 14 Week 14 Elizabeth Completed
Research Paper
Set up structure of research paper Week 3 Week 14 All Completed
Update research paper (iterative) Week 3 Week 14 All Completed
Poster
Create Poster Week 14 Week 14 All Completed

Work Plan

  • Fortnightly meetings with Supervisor
  • Monthly meetings with Sponsor
Hiryuu Gantt Chart.JPG

Weekly Diary