Project Schedule

Tasks Start Week End Week Team Members Involved Status
Requirements Gathering
Project Sponsor Confirmation
Week 0
Week 1
All
Completed
Define Project Scope
Week 0
Week 1
All
Completed
Data Collection
Gather Data from Sponsor
Week 0
Week 1
All
Completed
Project Proposal - Due on 8 January 2017
Proposal Preparation
Week 0
Week 1
All
Completed
Wiki Page Preparation
Week 0
Week 1
All
Completed
Data Preparation
Data Exploration (before system launch)
Week 2
-
All
In Progress
Data Cleaning (before system launch)
Week 2
-
All
In Progress
Data Transformation & Normalization (before system launch)
Week 2
-
All
In Progress
Data Exploration (after system launch)
-
-
-
Not Completed
Data Cleaning (after system launch)
-
-
-
Not Completed
Data Transformation & Normalization (after system launch)
-
-
-
Not Completed
Interim Practicum - Documents Due 19 February 2017
Report Preparation
-
-
-
Not Completed
Wiki Update
-
-
-
Not Completed
Presentation Preparation
-
-
-
Not Completed
Client Review
-
-
-
Not Completed
Interim Presentation
-
-
-
Not Completed
Visualization
Dashboard - Comparison of transactions before and after launch
-
-
-
Not Completed
Dashboard - New Customers
-
-
-
Not Completed
Insights & Recommendation
Insights Generation
-
-
-
Not Completed
Recommendation
-
-
-
Not Completed
Final - Full Paper Due 2nd April 2017, Final Paper Due 26th April 2017
Client Review
-
-
-
Not Completed
Report Preparation
-
-
-
Not Completed
Wiki Update
-
-
-
Not Completed
Presentation Preparation
-
-
-
Not Completed
Final Paper Revision
-
-
-
Not Completed
Conference
Undergraduate Conference on Data Analysis
-
-
-
Not Completed

Project Timeline

Group 2 Project Timeline.PNG

Timeline AP Group 2 Legend.PNG