Hiryuu Project Management

From Analytics Practicum
Revision as of 10:05, 31 December 2016 by Qianpin.lin.2013 (talk | contribs)
Jump to navigation Jump to search
Logo Hiryuu.png


Home

About Us

Project Overview

Findings

Project Management

Documentations

Timeline

Tasks Start End Teammates Involved Status
Data Gathering and Scoping
Gather Data Week 0 Week 0 All Completed
Finalise Requirements with client Week 0 Week 0 All Completed
Scope Project Week 0 Week 0 All Completed
Research and Preparation
Explore software Week 0 Week 0 All Completed
Finalise Proposal Week 0 Week 0 All Completed
Create and update wiki page Week 0 Week 0 All Completed
Data Cleaning
Data collection Week 1 Week 2 All Not Completed
Data cleaning and restructuring Week 1 Week 2 All Not Completed
Resolve/remove incomplete data Week 1 Week 2 All Not Completed
Data Modelling
Stage 1: Week 4 Week 4 Yi Sheng Completed
Data Cleaning Week 4 Week 8 All Completed
Modelling
Stage 1: Exploratory Analysis Week 4 Week 8 All Completed
Stage 2: Funnel Plot Analysis Week 7 Week 9 Elizabeth Completed
Stage 3: Time-Series Analysis Week 8 Week 10 Elizabeth & Kang Long Completed
Stage 4: Geospatial Analysis Week 7 Week 10 Yi Sheng Completed
Midterm Presentation
Create Midterm Report Week 7 Week 8 All Completed
Update Wiki Week 8 Week 8 Elizabeth Completed
Testing & Iteration
Stage 6: Refining and extrapolating Week 8 Week 13 All Completed
Meeting Client to get feedback Week 8 Week 13 All Completed
Refine Model based on feedback Week 8 Week 14 All Completed
Final Presentation
Prepare final presentation slides Week 14 Week 14 Kang Long & Yi Sheng Completed
Update Wiki Week 14 Week 14 Elizabeth Completed
Research Paper
Set up structure of research paper Week 3 Week 14 All Completed
Update research paper (iterative) Week 3 Week 14 All Completed
Poster
Create Poster Week 14 Week 14 All Completed

Work Plan

  • Fortnightly meetings with Supervisor
  • Monthly meetings with Sponsor
Hiryuu Gantt Chart.JPG

Weekly Diary