<p>The scope of work in this project can be split into 4 key phases. The first phase will be
 +
establishing the parameters of the project (from Week 0 to Week 2). During this phase, we
 +
will be in close contact with our sponsors, and the phase encompasses the project proposal
 +
submission milestone, resolution of administrative matters such as non-disclose agreement
 +
outlining, and acquisition of the data.</p>
 
<p>
 
<p>
The scope of work can be split 4 key phases. The first phase would be establishing the parameters of the project (from Week 0 to Week 2). During this phase, we would be in close contact with our sponsors, culminating in the milestone of our project proposal.
+
The second phase will be the preparation of the data (from Week 2 to Week 8). Here, we
The second phase would be the preparation of the data (from Week 2 to Week 8). Here, we would have obtained the data and we would employ various techniques to clean and make sense of the data.  
+
will have obtained the data and will begin exploratory data analysis and data cleaning.
The third phase would be building the model (Week 8 to Week 12). With the understanding of the data, we will create a model, following several rounds of iterations.
+
</p>
The final phase would be delivery of findings (Week 13 to Week 14). Here we would summarise our key findings for presentation.
+
<p>
 +
The third phase will be building the models (Week 8 to Week 12). With a clearer
 +
understanding of the data on hand, we will begin fitting the data to each model as
 +
appropriate, in a variety of ways in order to determine which is most successful.
 +
</p>
 +
<p>
 +
The final phase will be delivery of findings (Week 13 to Week 14). Here we will focus on
 +
crafting a clear technical explanation of our methodology and results, for the client,
 +
documentation, and hopefully publication.
 
</p>
 
</p>

Revision as of 23:37, 14 January 2018

Home   Project Overview   Findings & Insights   Documentation   Project Management   Back to project list


Project Management

JFI Gantt.png

The scope of work in this project can be split into 4 key phases. The first phase will be establishing the parameters of the project (from Week 0 to Week 2). During this phase, we will be in close contact with our sponsors, and the phase encompasses the project proposal submission milestone, resolution of administrative matters such as non-disclose agreement outlining, and acquisition of the data.

The second phase will be the preparation of the data (from Week 2 to Week 8). Here, we will have obtained the data and will begin exploratory data analysis and data cleaning.

The third phase will be building the models (Week 8 to Week 12). With a clearer understanding of the data on hand, we will begin fitting the data to each model as appropriate, in a variety of ways in order to determine which is most successful.

The final phase will be delivery of findings (Week 13 to Week 14). Here we will focus on crafting a clear technical explanation of our methodology and results, for the client, documentation, and hopefully publication.