Line 102: Line 102:
  
 
|-
 
|-
| Data Exploration
+
| Data Exploration (before system launch)
 
| <center>Week 2</center>
 
| <center>Week 2</center>
 
| <center>-</center>
 
| <center>-</center>
Line 110: Line 110:
  
 
|-
 
|-
| Data Cleaning
+
| Data Cleaning (before system launch)
 
| <center>Week 2</center>
 
| <center>Week 2</center>
 
| <center>-</center>
 
| <center>-</center>
Line 118: Line 118:
  
 
|-
 
|-
| Data Transformation & Normalization
+
| Data Transformation & Normalization (before system launch)
 
| <center>Week 2</center>
 
| <center>Week 2</center>
 
| <center>-</center>
 
| <center>-</center>
Line 126: Line 126:
  
 
|-
 
|-
|- style="background:black; color:white; text-align: left;"
+
| Data Exploration (after system launch)
|colspan="7"|'''Data Analysis (1)'''
+
| <center>Week 2</center>
 +
| <center>-</center>
 +
| <center>All</center>
 +
| style="background:PeachPuff"| <center>'''In Progress'''</center>
 
|-
 
|-
  
 
|-
 
|-
| Association Rule Mining
+
| Data Cleaning (after system launch)
 +
| <center>Week 2</center>
 
| <center>-</center>
 
| <center>-</center>
 +
| <center>All</center>
 +
| style="background:PeachPuff"| <center>'''In Progress'''</center>
 +
|-
 +
 +
|-
 +
| Data Transformation & Normalization (after system launch)
 +
| <center>Week 2</center>
 
| <center>-</center>
 
| <center>-</center>
| <center>-</center>
+
| <center>All</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| style="background:PeachPuff"| <center>'''In Progress'''</center>
 
|-
 
|-
  
Line 168: Line 179:
 
|-
 
|-
 
| Interim Presentation
 
| Interim Presentation
| <center>-</center>
 
| <center>-</center>
 
| <center>-</center>
 
| style="background:LightCoral"| <center>'''Not Completed'''</center>
 
|-
 
 
|-
 
|- style="background:black; color:white; text-align: left;"
 
|colspan="7"|'''Data Analysis (2)'''
 
|-
 
 
|-
 
| Correlation Analysis
 
 
| <center>-</center>
 
| <center>-</center>
 
| <center>-</center>
 
| <center>-</center>

Revision as of 19:07, 11 January 2017


HOME

 

PROJECT OVERVIEW

 

FINDINGS

 

PROJECT DOCUMENTATION

 

PROJECT MANAGEMENT

 

ANLY482 HOMEPAGE

Project Schedule

Tasks Start Week End Week Team Members Involved Status
Requirements Gathering
Project Sponsor Confirmation
Week 0
Week 1
All
Completed
Define Project Scope
Week 0
Week 1
All
Completed
Data Collection
Gather Data from Sponsor
Week 0
Week 1
All
Completed
Project Proposal - Due on 8 January 2017
Project Preparation
Week 0
Week 1
All
Completed
Wiki Page Preparation
Week 0
Week 1
All
Completed
Data Preparation
Data Exploration (before system launch)
Week 2
-
All
In Progress
Data Cleaning (before system launch)
Week 2
-
All
In Progress
Data Transformation & Normalization (before system launch)
Week 2
-
All
In Progress
Data Exploration (after system launch)
Week 2
-
All
In Progress
Data Cleaning (after system launch)
Week 2
-
All
In Progress
Data Transformation & Normalization (after system launch)
Week 2
-
All
In Progress
Interim Practicum - Documents Due 19 February 2017
Report Preparation
-
-
-
Not Completed
Wiki Update
-
-
-
Not Completed
Presentation Preparation
-
-
-
Not Completed
Interim Presentation
-
-
-
Not Completed
Visualization
Dashboard
-
-
-
Not Completed
Insights & Recommendation
Insights Generation
-
-
-
Not Completed
Recommendation
-
-
-
Not Completed
Final - Full Paper Due 2nd April 2017, Final Paper Due 26th April 2017
Report Preparation
-
-
-
Not Completed
Wiki Update
-
-
-
Not Completed
Presentation Preparation
-
-
-
Not Completed
Final Paper Revision
-
-
-
Not Completed
Conference
Undergraduate Conference on Data Analysis
-
-
-
Not Completed

Project Timeline

Group 2 Project Timeline.PNG

Timeline AP Group 2 Legend.PNG