Difference between revisions of "ANLY482 AY2017-18T2 Group30 Project Management"

From Analytics Practicum
Jump to navigation Jump to search
(Added in Gantt Chart till Interim presentation)
Line 168: Line 168:
 
|-
 
|-
 
|}
 
|}
<br>
 
 
<center>Updated as of <b>11/01/2018</b></center>
 
<center>Updated as of <b>11/01/2018</b></center>
 
 
 
<br/>
 
<br/>
 +
<div style=" background: #E6EDFA; padding: 10px; font-family: Arimo; font-size: 18px; font-weight: bold; line-height: 1em; text-indent: 15px; border-left: #5A6B96 solid 32px;"><font color="#5A6B96">Gantt Chart</font></div>
 +
<br/>
 +
<center>
 +
[[Image: Group 30 Gantt Chart.png | 1000px]]
 +
</center>

Revision as of 14:19, 12 January 2018


HOME ABOUT US PROJECT OVERVIEW PROJECT FINDINGS PROJECT MANAGEMENT DOCUMENTATION


Project Timeline


Tasks Start Week End Week Teammates Involved Status
Project Preparation
Understanding Sponsor Requirements Week 0 Week 1 All
In Progress
Create and Update Proposal Week 0 Week 1 All
In Progress
Create and Update Wikipedia Week 0 Week 1 All
In Progress
Project Acceptance Week 0 Week 1 All
TBC
Data Gathering & Scoping
Gather Data Week 1 Week 2 All
TBC
Finalize Requirements with Sponsor Week 1 Week 2 All
TBC
Scope Project Week 2 Week 2 All
TBC
Research & Preparation
Explore Software Week 2 Week 2 All
TBC
Finalize Proposal Week 2 Week 2 All
TBC
Data Cleaning
Data Collection Week 2 Week 3 All
TBC
Data Cleaning Week 4 Week 5 Ivan, Shing Hei
TBC
Data Transformation Week 5 Week 5 Eric
TBC
Data Modeling
Exploratory Analysis Week 6 Week 7 All
TBC
Interim Preparation
Gather Feedback from Sponsor Week 7 Week 7 All
TBC
Prepare Interim Report & Slides Week 7 Week 7 All
TBC
Buffer Week 7 Week 8 All
TBC
Updated as of 11/01/2018