*Proposal wiki updated
 +
*Proposal report updated
 +
*Interim wiki in-progress
 +
*Interim report in-progress
 +
*Interim slides updated
 +
<br>
 +
<p>We have finished our 4th wave of Exploratory Data Analysis (EDA). Different from the previous wave of EDA, the team looks at the general insight that can be found in all products before diving deeper into the respective product types. In this way, we will not have repetitive analysis as per those from the previous waves of EDA.
 +
Besides that, the team is also in the midst of constructing the dashboard. We have identified the main insights from our EDA and are reviewing these insights in the form of a dashboard.<br>
 +
We had issues with inconsistencies and abnormalities in the datasets previously, and were bumpy in ragging and exploring the data. But we managed to solve it swiftly and did not face any delay in our schedule.</p>
 +
</font>
 +
</div>
 +
 
==<div style="background: #6A8D9D; line-height: 0.3em; font-family:helvetica;  border-left: #466675 solid 15px;"><div style="border-left: #FFFFFF solid 5px; padding:15px;font-size:15px;"><font color= "#F2F1EF"><strong>Project Schedule</strong></font></div></div>==
 
==<div style="background: #6A8D9D; line-height: 0.3em; font-family:helvetica;  border-left: #466675 solid 15px;"><div style="border-left: #FFFFFF solid 5px; padding:15px;font-size:15px;"><font color= "#F2F1EF"><strong>Project Schedule</strong></font></div></div>==
 
<!--Table-->
 
<!--Table-->

Revision as of 21:58, 19 February 2017


HOME

 

FINDINGS

 

PROJECT DOCUMENTATION

 

PROJECT MANAGEMENT

 

ABOUT US

 

ANLY482 HOMEPAGE

Current Progress

  • Proposal wiki updated
  • Proposal report updated
  • Interim wiki in-progress
  • Interim report in-progress
  • Interim slides updated


We have finished our 4th wave of Exploratory Data Analysis (EDA). Different from the previous wave of EDA, the team looks at the general insight that can be found in all products before diving deeper into the respective product types. In this way, we will not have repetitive analysis as per those from the previous waves of EDA. Besides that, the team is also in the midst of constructing the dashboard. We have identified the main insights from our EDA and are reviewing these insights in the form of a dashboard.
We had issues with inconsistencies and abnormalities in the datasets previously, and were bumpy in ragging and exploring the data. But we managed to solve it swiftly and did not face any delay in our schedule.

Project Schedule

Tasks Start Week End Week Planned Man Hours Actual Man Hours Team Members Involved Status
Requirements Gathering
Project Sponsor Confirmation
Week 0
Week 1
5
5
All
Completed
Define Project Scope
Week 0
Week 1
10
10
All
Completed
Data Collection
Gather Data from Sponsor
Week 0
Week 1
3
3
All
Completed
Project Proposal - Due on 15 January 2017
Proposal Preparation
Week 0
Week 2
20
20
All
Completed
Wiki Page Preparation
Week 0
Week 2
10
10
All
Completed
Project Preparation
Literature Review
Week 2
-
6
-
All
In Progress
Data Preparation
Data Exploration (Dataset 1)
Week 2
-
24
-
All
In Progress
Data Cleaning (Dataset 1)
Week 2
-
20
-
Leejia
In Progress
Data Transformation & Normalization (Dataset 1)
Week 2
-
16
-
Jonathan
In Progress
Data Exploration (Dataset 2)
Week 3
-
20
-
All
Not Started
Data Cleaning (Dataset 2)
Week 3
-
14
-
Weifa
Not Started
Data Transformation & Normalization (Dataset 2)
Week 3
-
10
-
Jonathan
Not Started
Interim Practicum - Documents Due 19 February 2017
Report Preparation
Week 5
-
28
-
All
Not Started
Wiki Update
Week 5
-
15
-
Jonathan
Not Started
Presentation Preparation
Week 5
-
20
-
Leejia & Weifa
Not Started
Client Review
Week 6
-
6
-
All
Not Started
Interim Presentation
Week 8
-
3
-
All
Not Started
Visualization
Dashboard - Comparison of transactions before and after launch
Week 8
-
45
-
Leejia & Jonathan
Not Started
Dashboard - New Customers
Week 8
-
25
-
Weifa
Not Started
Insights & Recommendation
Insights Generation
Week 10
-
20
-
All
Not Started
Recommendation
Week 10
-
20
-
All
Not Started
Final - Full Paper Due 2nd April 2017, Final Paper Due 26th April 2017
Client Review
Week 12
-
6
-
All
Not Started
Report Preparation
Week 12
-
20
-
All
Not Started
Wiki Update
Week 12
-
5
-
Leejia
Not Started
Presentation Preparation
Week 12
-
15
-
Weifa & Jonathan
Not Started
Final Paper Revision
Week 14
-
20
-
All
Not Started
Conference
Undergraduate Conference on Data Analysis
Week 16
-
6
-
All
Not Started

Project Timeline

Group 2 Project Timeline.PNG

Timeline AP Group 2 Legend.PNG