Difference between revisions of "ANLY482 AY2016-17 T2 Group 2 Project Management"

From Analytics Practicum
Jump to navigation Jump to search
 
(13 intermediate revisions by 2 users not shown)
Line 4: Line 4:
 
{|style="background-color:#6A8D9D; color: #F5F5F5; padding: 10 0 10 0;" width="100%" cellspacing="0" cellpadding="0" valign="top" border="0" |
 
{|style="background-color:#6A8D9D; color: #F5F5F5; padding: 10 0 10 0;" width="100%" cellspacing="0" cellpadding="0" valign="top" border="0" |
 
| style="padding:0.3em; font-size:100%; background-color:#6A8D9D; text-align:center; color: #F5F5F5" width="10%" |
 
| style="padding:0.3em; font-size:100%; background-color:#6A8D9D; text-align:center; color: #F5F5F5" width="10%" |
[[ANLY482 AY2016-17 T2 Group 2|  
+
[[ANLY482_AY2016-17_T2_Group_2|  
 
<font color="#F5F5F5" size=2><b>HOME</b></font>]]
 
<font color="#F5F5F5" size=2><b>HOME</b></font>]]
  
 
| style="background:none;" width="1%" | &nbsp;
 
| style="background:none;" width="1%" | &nbsp;
 
| style="padding:0.3em; font-size:100%; background-color:#6A8D9D; text-align:center; color:#F5F5F5" width="10%" |  
 
| style="padding:0.3em; font-size:100%; background-color:#6A8D9D; text-align:center; color:#F5F5F5" width="10%" |  
[[ANLY482 AY2016-17 T2 Group 2 Project Overview|
+
[[ANLY482_AY2016-17_T2_Group_2 Findings|
<font color="#F5F5F5" size=2><b>PROJECT OVERVIEW</b></font>]]
 
 
 
| style="background:none;" width="1%" | &nbsp;
 
| style="padding:0.3em; font-size:100%; background-color:#6A8D9D; text-align:center; color:#F5F5F5" width="10%" |
 
[[ANLY482 AY2016-17 T2 Group 2 Findings|
 
 
<font color="#F5F5F5" size=2><b>FINDINGS</b></font>]]
 
<font color="#F5F5F5" size=2><b>FINDINGS</b></font>]]
  
 
| style="background:none;" width="1%" | &nbsp;
 
| style="background:none;" width="1%" | &nbsp;
 
| style="padding:0.3em; font-size:100%; background-color:#6A8D9D; text-align:center; color:#F5F5F5" width="10%" |  
 
| style="padding:0.3em; font-size:100%; background-color:#6A8D9D; text-align:center; color:#F5F5F5" width="10%" |  
[[ANLY482 AY2016-17 T2 Group 2 Project Documentation|
+
[[ANLY482_AY2016-17_T2_Group_2 Project Documentation|
 
<font color="#F5F5F5" size=2><b>PROJECT DOCUMENTATION</b></font>]]
 
<font color="#F5F5F5" size=2><b>PROJECT DOCUMENTATION</b></font>]]
  
 
| style="background:none;" width="1%" | &nbsp;
 
| style="background:none;" width="1%" | &nbsp;
 
| style="padding:0.3em; font-size:100%; background-color:#466675; text-align:center; color:#F5F5F5" width="10%" |  
 
| style="padding:0.3em; font-size:100%; background-color:#466675; text-align:center; color:#F5F5F5" width="10%" |  
[[ANLY482 AY2016-17 T2 Group 2 Project Management|
+
[[ANLY482_AY2016-17_T2_Group_2 Project Management|
 
<font color="#F5F5F5" size=2><b>PROJECT MANAGEMENT</b></font>]]
 
<font color="#F5F5F5" size=2><b>PROJECT MANAGEMENT</b></font>]]
 +
 +
| style="background:none;" width="1%" | &nbsp;
 +
| style="padding:0.3em; font-size:100%; background-color:#6A8D9D; text-align:center; color:#F5F5F5" width="10%" |
 +
[[ANLY482_AY2016-17_T2_Group_2 About Us|
 +
<font color="#F5F5F5" size=2><b>ABOUT US</b></font>]]
  
 
| style="background:none;" width="1%" | &nbsp;
 
| style="background:none;" width="1%" | &nbsp;
Line 35: Line 35:
  
 
<!--Content-->
 
<!--Content-->
 +
==<div style="background: #35404F; padding: 13px; font-weight: bold; text-align:center; line-height: 0.3em; text-indent: 20px;font-size:25px"><font color= #ffffff>Current Progress</font></div>==
 +
<div style="margin:20px; padding: 10px; background: #ffffff;  font-size: 95%;-webkit-border-radius: 15px;-webkit-box-shadow: 7px 4px 14px rgba(176, 155, 121, 0.96); -moz-box-shadow: 7px 4px 14px rgba(176, 155, 121, 0.96);box-shadow: 7px 4px 14px rgba(176, 155, 121, 0.96);">
 +
*Final wiki updated
 +
*Final slides updated
 +
*Final report updated
 +
</div>
 +
 
==<div style="background: #6A8D9D; line-height: 0.3em; font-family:helvetica;  border-left: #466675 solid 15px;"><div style="border-left: #FFFFFF solid 5px; padding:15px;font-size:15px;"><font color= "#F2F1EF"><strong>Project Schedule</strong></font></div></div>==
 
==<div style="background: #6A8D9D; line-height: 0.3em; font-family:helvetica;  border-left: #466675 solid 15px;"><div style="border-left: #FFFFFF solid 5px; padding:15px;font-size:15px;"><font color= "#F2F1EF"><strong>Project Schedule</strong></font></div></div>==
 +
<div style="margin:20px; padding: 10px; background: #ffffff;  font-size: 95%;-webkit-border-radius: 15px;-webkit-box-shadow: 7px 4px 14px rgba(176, 155, 121, 0.96); -moz-box-shadow: 7px 4px 14px rgba(176, 155, 121, 0.96);box-shadow: 7px 4px 14px rgba(176, 155, 121, 0.96);">
 +
 
<!--Table-->
 
<!--Table-->
 
+
{| class="wikitable" width="90%"
{| class="wikitable" width="70%"
 
 
|-
 
|-
 
! style="background:#B6B6B4"|Tasks
 
! style="background:#B6B6B4"|Tasks
 
! style="background:#B6B6B4" width="10%"|Start Week
 
! style="background:#B6B6B4" width="10%"|Start Week
 
! style="background:#B6B6B4" width="10%"|End Week
 
! style="background:#B6B6B4" width="10%"|End Week
! style="background:#B6B6B4" width="20%"|Team Members Involved
+
! style="background:#B6B6B4" width="12%"|Planned Man Hours
 +
! style="background:#B6B6B4" width="12%"|Actual Man Hours
 +
! style="background:#B6B6B4" width="15%"|Team Members Involved
 
! style="background:#B6B6B4" width="15%"|Status
 
! style="background:#B6B6B4" width="15%"|Status
 
|- style="background:black; color:white; text-align: left;"  
 
|- style="background:black; color:white; text-align: left;"  
Line 53: Line 63:
 
| <center>Week 0</center>
 
| <center>Week 0</center>
 
| <center>Week 1</center>
 
| <center>Week 1</center>
 +
| <center>5</center>
 +
| <center>5</center>
 
| <center>All</center>
 
| <center>All</center>
 
| style="background:aquamarine"| <center>'''Completed'''</center>
 
| style="background:aquamarine"| <center>'''Completed'''</center>
Line 61: Line 73:
 
| <center>Week 0</center>
 
| <center>Week 0</center>
 
| <center>Week 1</center>
 
| <center>Week 1</center>
 +
| <center>10</center>
 +
| <center>10</center>
 
| <center>All</center>
 
| <center>All</center>
 
| style="background:aquamarine"| <center>'''Completed'''</center>
 
| style="background:aquamarine"| <center>'''Completed'''</center>
Line 73: Line 87:
 
| <center>Week 0</center>
 
| <center>Week 0</center>
 
| <center>Week 1</center>
 
| <center>Week 1</center>
 +
| <center>3</center>
 +
| <center>3</center>
 
| <center>All</center>
 
| <center>All</center>
 
| style="background:aquamarine"| <center>'''Completed'''</center>
 
| style="background:aquamarine"| <center>'''Completed'''</center>
Line 78: Line 94:
  
 
|- style="background:black; color:white; text-align: left;"  
 
|- style="background:black; color:white; text-align: left;"  
|colspan="7"|'''Project Proposal - Due on 8 January 2017'''
+
|colspan="7"|'''Project Proposal - Due on 15 January 2017'''
 
|-
 
|-
  
 
|-
 
|-
| Project Preparation
+
| Proposal Preparation
 
| <center>Week 0</center>
 
| <center>Week 0</center>
| <center>Week 1</center>
+
| <center>Week 2</center>
 +
| <center>20</center>
 +
| <center>20</center>
 
| <center>All</center>
 
| <center>All</center>
 
| style="background:aquamarine"| <center>'''Completed'''</center>
 
| style="background:aquamarine"| <center>'''Completed'''</center>
Line 92: Line 110:
 
| Wiki Page Preparation
 
| Wiki Page Preparation
 
| <center>Week 0</center>
 
| <center>Week 0</center>
| <center>Week 1</center>
+
| <center>Week 2</center>
 +
| <center>10</center>
 +
| <center>10</center>
 +
| <center>All</center>
 +
| style="background:aquamarine"| <center>'''Completed'''</center>
 +
|-
 +
 
 +
 
 +
|- style="background:black; color:white; text-align: left;"
 +
|colspan="7"|'''Project Preparation'''
 +
|-
 +
 
 +
|-
 +
| Literature Review
 +
| <center>Week 2</center>
 +
| <center>Week 3</center>
 +
| <center>6</center>
 +
| <center>8</center>
 
| <center>All</center>
 
| <center>All</center>
 
| style="background:aquamarine"| <center>'''Completed'''</center>
 
| style="background:aquamarine"| <center>'''Completed'''</center>
Line 102: Line 137:
  
 
|-
 
|-
| Data Exploration
+
| Data Exploration (Musical Dataset)
 
| <center>Week 2</center>
 
| <center>Week 2</center>
| <center>-</center>
+
| <center>Week 3</center>
 +
| <center>24</center>
 +
| <center>30</center>
 
| <center>All</center>
 
| <center>All</center>
| style="background:PeachPuff"| <center>'''In Progress'''</center>
+
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|-
 
|-
| Data Cleaning
+
| Data Cleaning (Musical Dataset)
 
| <center>Week 2</center>
 
| <center>Week 2</center>
| <center>-</center>
+
| <center>Week 3</center>
| <center>All</center>
+
| <center>20</center>
| style="background:PeachPuff"| <center>'''In Progress'''</center>
+
| <center>20</center>
 +
| <center>Leejia</center>
 +
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|-
 
|-
| Data Transformation & Normalization
+
| Data Transformation & Normalization (Musical Dataset)
 
| <center>Week 2</center>
 
| <center>Week 2</center>
| <center>-</center>
+
| <center>Week 3</center>
 +
| <center>16</center>
 +
| <center>20</center>
 +
| <center>Jonathan</center>
 +
| style="background:aquamarine"| <center>'''Completed'''</center>
 +
|-
 +
 
 +
|-
 +
| Data Exploration (Concert Dataset)
 +
| <center>Week 4</center>
 +
| <center>Week 6</center>
 +
| <center>20</center>
 +
| <center>35</center>
 
| <center>All</center>
 
| <center>All</center>
| style="background:PeachPuff"| <center>'''In Progress'''</center>
+
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|-
 
|-
|- style="background:black; color:white; text-align: left;"
+
| Data Cleaning (Concert Dataset)
|colspan="7"|'''Data Analysis (1)'''
+
| <center>Week 4</center>
 +
| <center>Week 6</center>
 +
| <center>14</center>
 +
| <center>25</center>
 +
| <center>Weifa</center>
 +
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|-
 
|-
| Association Rule Mining
+
| Data Transformation & Normalization (Concert Dataset)
| <center>-</center>
+
| <center>Week 4</center>
| <center>-</center>
+
| <center>Week 6</center>
| <center>-</center>
+
| <center>10</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| <center>20</center>
 +
| <center>Jonathan</center>
 +
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|- style="background:black; color:white; text-align: left;"  
 
|- style="background:black; color:white; text-align: left;"  
|colspan="7"|'''Interim Practicum - Documents Due 19 February 2017'''
+
|colspan="7"|'''Interim Practicum - Documents Due 26 February 2017'''
 
|-
 
|-
  
 
|-
 
|-
 
| Report Preparation
 
| Report Preparation
| <center>-</center>
+
| <center>Week 5</center>
| <center>-</center>
+
| <center>Week 7</center>
| <center>-</center>
+
| <center>28</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| <center>30</center>
 +
| <center>All</center>
 +
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|-
 
|-
 
| Wiki Update
 
| Wiki Update
| <center>-</center>
+
| <center>Week 5</center>
| <center>-</center>
+
| <center>Week 7</center>
| <center>-</center>
+
| <center>15</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| <center>15</center>
 +
| <center>Jonathan</center>
 +
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|-
 
|-
 
| Presentation Preparation
 
| Presentation Preparation
| <center>-</center>
+
| <center>Week 5</center>
| <center>-</center>
+
| <center>Week 7</center>
| <center>-</center>
+
| <center>20</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| <center>30</center>
 +
| <center>Leejia & Weifa</center>
 +
| style="background:aquamarine"| <center>'''Completed'''</center>
 +
|-
 +
 
 +
|-
 +
| Client Review
 +
| <center>Week 6</center>
 +
| <center>Week 7</center>
 +
| <center>6</center>
 +
| <center>6</center>
 +
| <center>All</center>
 +
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|-
 
|-
 
| Interim Presentation
 
| Interim Presentation
 +
| <center>Week 8</center>
 
| <center>-</center>
 
| <center>-</center>
 +
| <center>3</center>
 
| <center>-</center>
 
| <center>-</center>
| <center>-</center>
+
| <center>All</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|-
 
|-
 
|- style="background:black; color:white; text-align: left;"  
 
|- style="background:black; color:white; text-align: left;"  
|colspan="7"|'''Data Analysis (2)'''
+
|colspan="7"|'''Visualization'''
 
|-
 
|-
  
 
|-
 
|-
| Correlation Analysis
+
| Dashboard - Comparison of transactions before and after launch
 +
| <center>Week 8</center>
 
| <center>-</center>
 
| <center>-</center>
 +
| <center>45</center>
 
| <center>-</center>
 
| <center>-</center>
| <center>-</center>
+
| <center>Leejia & Jonathan</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| style="background:aquamarine"| <center>'''Completed'''</center>
|-
 
 
 
|-
 
|- style="background:black; color:white; text-align: left;"
 
|colspan="7"|'''Visualization'''
 
 
|-
 
|-
  
 
|-
 
|-
| Dashboard
+
| Dashboard - New Customers
 +
| <center>Week 8</center>
 
| <center>-</center>
 
| <center>-</center>
 +
| <center>25</center>
 
| <center>-</center>
 
| <center>-</center>
| <center>-</center>
+
| <center>Weifa</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
Line 208: Line 283:
 
|-
 
|-
 
| Insights Generation
 
| Insights Generation
 +
| <center>Week 10</center>
 
| <center>-</center>
 
| <center>-</center>
 +
| <center>20</center>
 
| <center>-</center>
 
| <center>-</center>
| <center>-</center>
+
| <center>All</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|-
 
|-
 
| Recommendation
 
| Recommendation
 +
| <center>Week 10</center>
 
| <center>-</center>
 
| <center>-</center>
 +
| <center>20</center>
 
| <center>-</center>
 
| <center>-</center>
| <center>-</center>
+
| <center>All</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
Line 226: Line 305:
 
|colspan="7"|'''Final - Full Paper Due 2nd April 2017, Final Paper Due 26th April 2017'''
 
|colspan="7"|'''Final - Full Paper Due 2nd April 2017, Final Paper Due 26th April 2017'''
 
|-
 
|-
 +
 +
|-
 +
| Client Review
 +
| <center>Week 12</center>
 +
| <center>-</center>
 +
| <center>6</center>
 +
| <center>-</center>
 +
| <center>All</center>
 +
| style="background:aquamarine"| <center>'''Completed'''</center>
 +
|-
 +
  
 
|-
 
|-
 
| Report Preparation
 
| Report Preparation
 +
| <center>Week 12</center>
 
| <center>-</center>
 
| <center>-</center>
 +
| <center>20</center>
 
| <center>-</center>
 
| <center>-</center>
| <center>-</center>
+
| <center>All</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|-
 
|-
 
| Wiki Update
 
| Wiki Update
 +
| <center>Week 12</center>
 
| <center>-</center>
 
| <center>-</center>
 +
| <center>5</center>
 
| <center>-</center>
 
| <center>-</center>
| <center>-</center>
+
| <center>Leejia</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|-
 
|-
 
| Presentation Preparation
 
| Presentation Preparation
 +
| <center>Week 12</center>
 
| <center>-</center>
 
| <center>-</center>
 +
| <center>15</center>
 
| <center>-</center>
 
| <center>-</center>
| <center>-</center>
+
| <center>Weifa & Jonathan</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|-
 
|-
 
| Final Paper Revision
 
| Final Paper Revision
 +
| <center>Week 14</center>
 
| <center>-</center>
 
| <center>-</center>
 +
| <center>20</center>
 
| <center>-</center>
 
| <center>-</center>
| <center>-</center>
+
| <center>All</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
Line 266: Line 364:
 
|-
 
|-
 
| Undergraduate Conference on Data Analysis
 
| Undergraduate Conference on Data Analysis
 +
| <center>Week 16</center>
 
| <center>-</center>
 
| <center>-</center>
 +
| <center>6</center>
 
| <center>-</center>
 
| <center>-</center>
| <center>-</center>
+
| <center>All</center>
| style="background:LightCoral"| <center>'''Not Completed'''</center>
+
| style="background:aquamarine"| <center>'''Completed'''</center>
 
|-
 
|-
  
 
|}
 
|}
 +
</div>
  
 
==<div style="background: #6A8D9D; line-height: 0.3em; font-family:helvetica;  border-left: #466675 solid 15px;"><div style="border-left: #FFFFFF solid 5px; padding:15px;font-size:15px;"><font color= "#F2F1EF"><strong>Project Timeline</strong></font></div></div>==
 
==<div style="background: #6A8D9D; line-height: 0.3em; font-family:helvetica;  border-left: #466675 solid 15px;"><div style="border-left: #FFFFFF solid 5px; padding:15px;font-size:15px;"><font color= "#F2F1EF"><strong>Project Timeline</strong></font></div></div>==

Latest revision as of 23:17, 23 April 2017


HOME

 

FINDINGS

 

PROJECT DOCUMENTATION

 

PROJECT MANAGEMENT

 

ABOUT US

 

ANLY482 HOMEPAGE

Current Progress

  • Final wiki updated
  • Final slides updated
  • Final report updated

Project Schedule

Tasks Start Week End Week Planned Man Hours Actual Man Hours Team Members Involved Status
Requirements Gathering
Project Sponsor Confirmation
Week 0
Week 1
5
5
All
Completed
Define Project Scope
Week 0
Week 1
10
10
All
Completed
Data Collection
Gather Data from Sponsor
Week 0
Week 1
3
3
All
Completed
Project Proposal - Due on 15 January 2017
Proposal Preparation
Week 0
Week 2
20
20
All
Completed
Wiki Page Preparation
Week 0
Week 2
10
10
All
Completed
Project Preparation
Literature Review
Week 2
Week 3
6
8
All
Completed
Data Preparation
Data Exploration (Musical Dataset)
Week 2
Week 3
24
30
All
Completed
Data Cleaning (Musical Dataset)
Week 2
Week 3
20
20
Leejia
Completed
Data Transformation & Normalization (Musical Dataset)
Week 2
Week 3
16
20
Jonathan
Completed
Data Exploration (Concert Dataset)
Week 4
Week 6
20
35
All
Completed
Data Cleaning (Concert Dataset)
Week 4
Week 6
14
25
Weifa
Completed
Data Transformation & Normalization (Concert Dataset)
Week 4
Week 6
10
20
Jonathan
Completed
Interim Practicum - Documents Due 26 February 2017
Report Preparation
Week 5
Week 7
28
30
All
Completed
Wiki Update
Week 5
Week 7
15
15
Jonathan
Completed
Presentation Preparation
Week 5
Week 7
20
30
Leejia & Weifa
Completed
Client Review
Week 6
Week 7
6
6
All
Completed
Interim Presentation
Week 8
-
3
-
All
Completed
Visualization
Dashboard - Comparison of transactions before and after launch
Week 8
-
45
-
Leejia & Jonathan
Completed
Dashboard - New Customers
Week 8
-
25
-
Weifa
Completed
Insights & Recommendation
Insights Generation
Week 10
-
20
-
All
Completed
Recommendation
Week 10
-
20
-
All
Completed
Final - Full Paper Due 2nd April 2017, Final Paper Due 26th April 2017
Client Review
Week 12
-
6
-
All
Completed
Report Preparation
Week 12
-
20
-
All
Completed
Wiki Update
Week 12
-
5
-
Leejia
Completed
Presentation Preparation
Week 12
-
15
-
Weifa & Jonathan
Completed
Final Paper Revision
Week 14
-
20
-
All
Completed
Conference
Undergraduate Conference on Data Analysis
Week 16
-
6
-
All
Completed

Project Timeline

Group 2 Project Timeline.PNG

Timeline AP Group 2 Legend.PNG