SMT483G1: Anly.io Project Management
Project Plan
End of Week | Milestone | Features | |
---|---|---|---|
1 | Discuss Specifications and Logistics with Sponsor Show UI/UX Mockup to Sponsor (7 Jan) Design UI/UX |
Main Page | |
2 | Develop Front-end Develop Back-end |
Game | |
3 | Develop Back-end | Login and administration | |
4 | Showcase a Minimum Viable Product to Sponsor (31 Jan) | ||
5 | User Acceptance Test (1st round) (3-9 Feb) | ||
6 | Refine usability | Complete Learning Path of “Quests” Develop Buffer Feature |
|
7 | Mid-term Presentation and Report | ||
8 | User Acceptance Test (2nd round) (24-29 Feb) | ||
9 | Refine usability | ||
10 | Deploy to Cloud Go Live |
||
11 | User Acceptance Test (3rd round) (16-22 Mar) | ||
12 | Refine Usability CI/CD Prepare Demo and Presentation |
||
13 | Develop Business Model and Go-to Market Strategy CI/CD Prepare Report |
||
14 | Final Presentation | ||
15 | Report Submission |
Risks and Assumptions
Assumptions
1. Teachers are willing to try teaching using games
2. A cloud-based system by subscription is suitable for MOE's requirements in terms of security and
cost-effectiveness
3. A single platform is able to meet the learning needs of both IP, express and normal stream students
Risks
1. Schedule backlog due to fundamental changes required after user testing
Mitigation: plan schedule with buffer to cater for overrun
2. Data privacy risk from collecting student and staff details
Mitigation: encrypt student details and other important information when storing them on cloud platform
3. Insufficient product validation for commercialisation
Mitigation: conduct user acceptance tests on a variety of schools with mix of IP, express and normal stream
students to ensure good product fit