Project Plan
| End of Week | Milestone | Features | |
|---|---|---|---|
| 1 | Discuss Specifications and Logistics with Sponsor Show UI/UX Mockup to Sponsor (7 Jan) Design UI/UX | Main Page | |
| 2 | Develop Front-end Develop Back-end | Game | |
| 3 | Develop Back-end | Login and administration | |
| 4 | Showcase a Minimum Viable Product to Sponsor (31 Jan) | ||
| 5 | User Acceptance Test (1st round) (3-9 Feb) | ||
| 6 | Refine usability | Complete Learning Path of “Quests” Develop Buffer Feature | |
| 7 | Mid-term Presentation and Report | ||
| 8 | User Acceptance Test (2nd round) (24-29 Feb) | ||
| 9 | Refine usability | ||
| 10 | Deploy to Cloud Go Live | ||
| 11 | User Acceptance Test (3rd round) (16-22 Mar) | ||
| 12 | Refine Usability CI/CD Prepare Demo and Presentation | ||
| 13 | Develop Business Model and Go-to Market Strategy CI/CD Prepare Report | ||
| 14 | Final Presentation | ||
| 15 | Report Submission | 