Modules Total Completed Remaining Status Confident Level (0-1) Comment % Total Done
Account 3 3 0 100% 1 Fully deployed and tested -
Food 3 3 0 100% 1 Fully deployed and tested
Activity 6 6 0 100% 1 Fully deployed and tested
Event 4 3 1 75% 1 1 more tertiary function left to do after Mid Terms milestone
Affective 1 0 1 0% 1 To be implemented after Mid Terms milestone
Social 2 0 2 0% 1 To be implemented next iteration
Analytical 1 0 1 0% 1 To be implemented next iteration
Friends 2 2 0 100% 1 Fully deployed and tested
Notifications 2 2 0 100% 1 Fully deployed and tested
Management 4 0 4 0% 1 Sean will be implementing the front-end, Guan Ze will be implementing the back-end.



TheBrosCode PROJECT SCHEDULE header.png



Iterations Planned Actual Comments
1 Account Module 23 May 2018 24 May 2018 Sean and Guan Ze went for OCSP so team was short of manpower. Delayed for 1 day.
2 Food Module 12 June 2018 12 June 2018 Everything went as plan
3 Activity Module 1 July 2018 1 July 2018 One of the hardest and most complicated module in this entire project. Everyone worked hard and the team managed to complete the iteration within the timeframe.
4 Events Module 18 July 2018 18 July 2018 Everything went as plan
5 Regression Testing 28 July 2018 28 July 2018 Everything went as plan
User Acceptance Testing 1 3 August 2018 3 August 2018 Everything went as plan. Had 30 participants participated in the user testing
6 Acceptance 17 August 2018 17 August 2018 Completed our Acceptance milestone.
7 Friends Module 22 August 2018 22 August 2018 A interesting module that we are excited about. Allowing us to add friends.
Notifications Module 25 August 2018 25 August 2018 One of the hardest module due to the different scenarios that user might face. Everything went as plan.
8 Analytical Module 4 September 2018 Have not implemented
Social Module 7 September 2018 Have not implemented
TheBrosCode TaskMetricHeader.png
TheBrosCode TaskMetric8.PNG


TheBrosCode BugMetricHeader.png
TheBrosCode NumBugs1.PNG
TheBrosCode BugsScore1.PNG
TheBrosCode BugsBreakdown1.PNG



TheBrosCode PROJECT RISK.png



Risk Probability Impact Mitigation
Runkicker may not be able to operate on phones that do not meet the minimum SDK version of the app. High Low The team has to ensure that Runkicker supports not only the latest SDK version, but also several older versions in order to reach a wider population.
The Frontend / Backend development of the mobile app partially relies on online libraries to help speed up the team's progress, however there might be incompatible versions / outdated libraries. High Low The team is required to research and test the libraries thoroughly before implementing any of it into the mobile app.
As the target audience of the mobile app can range from unmotivated to obese / overweight individuals, finding such users can be a challenging and sensitive task for the team. High High The team is required to have EARLY planning of User Testing sessions internally and also to liaise with sponsors, to see if it is possible to work together with enterprise or government bodies to assist with the testing of the mobile app.



TheBrosCode INTERMEDIATE DELIVERABLES.png



Stage Specification Modules
Project Management Meeting Minutes TheBrosCode MeetingMinutes
Task Metrics TheBrosCode Metrics
Bug Metrics TheBrosCode BugMetric
Analysis Use Case Diagram TheBrosCode Documentation
Design ER Diagram TheBrosCode ERDiagram