Line 186: Line 186:
 
=== Technical Complexity(Details to be added ASAP) ===
 
=== Technical Complexity(Details to be added ASAP) ===
 
====AJAX auto-population of fields====
 
====AJAX auto-population of fields====
 +
Using AJAX technologies, we help increase the efficiency and decrease error when entering artist information. When the top admin / admin assistant enter the artist name, auto-suggestion using name's already in the database will be done. This increase their efficieny when they have to enter another product by the same artist as it reduce time to enter the same artist information again. And it decrease repeated artist information in the database.
 +
 +
It is complex as AJAX is completely new to most of the team members and it took a while for us to realise that it is done using AJAX even though we've seen something similar done in places such as facebook's search function
 +
 
====PDF Generation====
 
====PDF Generation====
 
====Facebook / Twitter sharing====
 
====Facebook / Twitter sharing====

Revision as of 20:27, 27 November 2010

Project Progress Summary

Since after the acceptance stage, our team had made a significant progress with the project. During the 6-week time, we could accomplish 2 of our milestones set, resulting in a fully-functioning store front and most importantly, the simple and effective back end interface specially designed for the disabled friends.

Project Highlights

There were no changes in scope of the project at that point of time.

Project Management

Project Status

Functional Requirement Status (% done) Confidence Level (0~1) Member in charge
Modifying Existing System 100% (fully deployed and tested) 1 Erene
Shopping Cart 100% (fully deployed and tested) 1 Din
Order History 100% (fully deployed and tested) 1 Erene
Manage Customer's Account Settings 100% (fully deployed and tested) 1 Kyaw
Donation 100% (fully deployed and tested) 1 Kyaw
Discount 100% (fully deployed and tested) 1 Soe Thet
Modify User Permission 100% (fully deployed and tested) 1 Kyaw
Back End UI 85% 0.95 Lu Mon
Customer Relationship Management 10% 0.85 Soe Thet
Tell Friends/A Friend 15% 0.9 Kyaw
Report Generation 0% 0.7 Erene
Shipping Module 0% 0.8 Kyaw
New Front End UI 15% 0.85 Soe Thet
Mobile Interface 0% 0.7 Soe Thet

Project Schedule

As mentioned earlier, our team is using the SCRUM framework. So, all the sprints throughout the project have the fixed duration (15 days in our case). And each sprint has one or more iterations in it. As the lengths of each sprint is fixed, the start and end dates of the sprints will be the same for both Planned and Actual Schedules. The only timelines affected (if there is) will be the lengths of the iterations. So, here, we will compare the planned and actual schedules of the iterations involved from the start till the midterm stage of the project.

Iteration Functional Requirement Planned End Date Actual End Date Comments
1 Research & Learning 11 Aug 11 Aug As per planned
2 Modifying Existing System 16 Aug 16 Aug As per planned
3 Shopping Cart 23 Aug 23 Aug As per planned
4 Order History 25 Aug 27 Aug Erene had to spend some time to look into the codes to edit
Manage Customer's Account Settings 27 Aug 31 Aug Kyaw had to take some time to figure out the optimal layout for the page
5 Donation 7 Sept 10 Sept Using PayPal for the very first time, it took Kyaw longer than expected to get it actually work
Discount 13 Sept 15 Sept The client took some time to let us know the most suitable discount type for FDS products; so, Soe Thet could only start working on it a few days later than planned
6 Modify User Permission 20 Sept 20 Sept As per planned
7 Back End UI 20 Sept 22 Sept It took longer than expected for us to come up with the most intuitive and simplest UI for disabled friends

Project Metrics

Our Schedule Metric shows that we were behind the schedule by a significant extent during Iterations 4 and 7. This is mainly because Iteration 4 was our very first time looking deep into the codes and adding in our own. So, it took some time for us to figure out if it is the right action or not. And for Iteration 7, it fell during the midterm weeks and so, all of us were obviously occupied by midterms and proposal submissions for projects.

From our Bug Metric, we can observe that we had some bugs of higher severity as we added in new modules to the existing system. However, we believe these all will gradually become fewer as we move on to the second half of the project.

Detailed Calculation Methods and Action Plans for each metric can be seen here.

Project Risks

If you compare the following risks to those at the initial stage, you will see that only two out of four risks remained. We overcame the other two risks from the initial stage by employing the mitigation plans and we succeeded. For example, for being unfamiliar with php, our team did spend much time on learning it in depth while helping each other out for a faster learning. Similarly, we also set aside a specific time in our schedule to understand how OpenCart works which helped us a lot as we progressed.

Meanwhile, the last two risks from the intial stage remained to be there at the midterm stage as our team felt that those are the risks that cannot be completely removed. However, as we had learned more about the end users' behaviors, we understood more about the impact of each risk on them. For example, from our experience with the real users during UAT 1, we had observed that the look and feel is really crucial for our target users. So, the impact level was increased making the risk level higher than the one we thought at the intial stage.

Risks Likelihood Impact Risk Level Mitigation Plans
Look and feel of the application does not meet the end users’ needs Moderate High High Perform UAT with the real end users and gather feedback to ensure a design that appeals to them
Maintenance of the system by the client High Low Moderate Schedule some trainings for the client/admin of the system at the end of the project

Technical Complexity(Details to be added ASAP)

AJAX auto-population of fields

Using AJAX technologies, we help increase the efficiency and decrease error when entering artist information. When the top admin / admin assistant enter the artist name, auto-suggestion using name's already in the database will be done. This increase their efficieny when they have to enter another product by the same artist as it reduce time to enter the same artist information again. And it decrease repeated artist information in the database.

It is complex as AJAX is completely new to most of the team members and it took a while for us to realise that it is done using AJAX even though we've seen something similar done in places such as facebook's search function

PDF Generation

Facebook / Twitter sharing

Quality of Product

Intermediate Deliverables

Deployment

Deployments to production site are made after each Sprint (refer to SCRUM framework). No testing server is given for this project so we also use production server as testing server since there will be no real transactions or activities before the website actually goes live. The URL for e-commerce homepage is http://shop.fds.org.sg/ and the URL for admin interface is http://shop.fds.org.sg/admin/ . Since the website is hosted on a shared hosting account with cPanel and no svn is setup on it, the deployment process is manual uploading of the files using FTP.

Testing

UAT 1 with client and disabled friends
Testers - Client, Disabled friend from FDS
Location - FDS
Duration - 3 hours
We had our very first UAT with the client while we were working on our second milestone. That UAT was focused more on the complete store front with partially done back-end interface. We got quite a lot of constructive feedback from the client and also from the disabled friends although there were no major changes demanded by them. However, negetive feedback outweigh the positive ones for our first UAT as you can see here.

Reflection

Team Reflection

Working together as a team on this project throughout these weeks, our team has learned learned how to manage the stakeholders (Supervisor/Client/Sponsor) and the team itself. We learnt how to manage client's expectations and how to wisely plan the limited resources (Manpower/Time) while applying the IT knowledge in real-life business.

And specifically from this FDS project, we have gained a lot of improvements in the aspects of php and creating simple and intuitive UI designs for disabled friends. Furthermore, we also have enhanced our soft skills like project management skills, research skills and learning-to-learn skills.

Benjamin Gan Reflection


Go To

Main Page
Final Wiki