Schedule Metric (Midterm)
We use Overtime % for Schedule Metric. We calculate our Overtime % according to the below method. First, we subtract actual time from planned time, divide the result by plan time and then multiply it with 100%. Actual time is the time duration we took to finish the functions within an iteration ,and planned time is the time duration we had planned to finish the functions within an iteration.