Project Progress Summary

This section only covers the progress of the project. For more detailed information, refer to our main wiki page here.
The following functions are completed.

  • Registration of a new account
  • Login and Logout
  • Creating of new lifestyle and tagging a project to it.
  • Uploading of picture from camera and library
  • Randomizing of projects for users
  • Filtering of projects by category
  • Contribution via PayPal


Project Highlights

  • Total of 2 changes raised while development. For more information, click here.
  • A total of 58 testers attended our first UAT. Our targeted size was 50.
  • PayPal API did not function correctly days before UAT.

Project Management

Project Status

Project Schedule (Plan VS Actual)

Project Metrics

Schedule Metric:
SPI.png


Bug Metric:
BSP.png


Project Risks

Technical Complexity

Quality of Product

Intermediate Deliverables

Deployment

UAT

The plan for our 1st UAT
While we aimed for 50 testers, a total of 58 testers attended our UAT.
The UAT was carried out over 2 days, 21st and 22nd Sept and 6 devices were deployed.
5 bugs were found during UAT and we had logged it here.

At the end of the testing, testers rated the ease of using our application and the overall user experience.

The results are shown as below:
Ease of using.png

  • 0% for Very Difficult, hence not shown in pie chart.

Overall exp.png

  • 0% for Very Bad, hence not shown in pie chart.

Reflection

Team Reflection

Daniel Reflection

Eugene Reflection

Hui Juan Reflection

Roger Reflection