Schedule of Web Application
Task no. | Description | Planned Start Date | Planned End Date | Actual End Date | Comments |
---|---|---|---|---|---|
Week of 29 November 2010 to 4 December 2010 | |||||
1 | Define Functionalities for Project Scope | 2010-11-29 | 2010-11-29 | 2010-11-29 | |
2 | Set Milestones and Targetted Goals | 2010-11-30 | 2010-11-30 | 2010-11-30 | |
3 | Create Project Management Gantt Chart | 2010-12-01 | 2010-12-01 | 2010-12-01 | |
Week of 05 December 2010 to 11 December 2010 | |||||
4 | Research ASP/Flash Connections for Web App | 2010-12-05 | 2010-12-07 | 2010-12-07 | |
5 | Specify Functionalities for Web app | 2010-12-08 | 2010-12-08 | 2010-12-08 | |
6 | Create Diagrams (Deployment, Solutions Architecture, ER, Use Case) | 2010-12-09 | 2010-12-09 | 2010-12-09 | |
7 | Design User Interface for Web app (Storyboard) | 2010-12-09 | 2010-12-09 | 2010-12-09 | |
8 | Develop User Interface for Web app | 2010-12-10 | 2010-12-10 | 2010-12-10 | |
9 | Design RWS Itinerary and USS Itinerary List View in Microsoft Powerpoint | 2010-12-10 | 2010-12-10 | 2010-12-10 | |
10 | Develop algorithm for Web app and Mobile web app in Excel (for RWS approval) | 2010-12-10 | 2010-12-10 | 2010-12-10 | |
Week of 12 December 2010 to 18 December 2010 | |||||
11 | Web app: Create User Form using Adobe Flash | 2010-12-12 | 2010-12-14 | 2010-12-14 | |
12 | Develop RWS itinerary selection model in excel | 2010-12-12 | 2010-12-17 | 2010-12-17 | |
Week of 19 December 2010 to 25 December 2010 | |||||
13 | Web app: Implement RWS itinerary selection model using excel | 2010-12-18 | 2010-12-22 | 2010-12-22 | |
14 | Implement display of RWS itinerary list view in ASP.NET (static itinerary with no algorithm) | 2010-12-23 | 2010-12-25 | 2010-12-25 | |
Week of 26 December 2010 to 01 January 2011 | |||||
15 | Test and Improve features in Management Portal for Project Acceptance Presentation | 2010-12-26 | 2010-12-27 | 2010-12-27 | |
16 | Integrate Web app with Excel database | 2010-12-26 | 2010-12-27 | 2010-12-27 | |
17 | Improve User Interface of Flash user form for Project Acceptance Presentation | 2010-12-29 | 2010-12-29 | 2010-12-29 | |
Week of 02 January 2011 to 08 January 2011 (SMU Week 1) | |||||
18 | Create Connection between ASP and Flash (prototype) | 2011-01-04 | 2011-01-06 | 2011-01-06 | |
19 | Improve User Interface for Flash User Form | 2011-01-06 | 2011-01-08 | 2011-01-08 | |
20 | Research and create prototype of drag-and-drop feature (allow patron to customise itinerary) | 2011-01-06 | 2011-01-08 | 2011-01-08 | |
Week of 09 January 2011 to 15 January 2011 (SMU Week 2) | |||||
21 | Web app: WebApp on localhost, timeline, drag&drop feature integrated (prototype) | 2011-01-09 | 2011-01-11 | 2011-01-11 | |
22 | Web app: Allow for double-click to edit duration when customising itinerary | 2011-01-12 | 2011-01-14 | Improve design: can utilise canvas space | |
Week of 16 January 2011 to 22 January 2011 (SMU Week 3) | |||||
23 | Web app: Allow for double-click to edit duration when customising itinerary | 2011-01-16 | 2011-01-18 | 2011-01-18 | onClick to view edit duration at bottom of page |
24 | Web app: WebApp deployed on server, timeline, drag&drop feature integrated | 2011-01-16 | 2011-01-18 | Server not up yet, will be deployed on 25Jan 2011 | |
25 | Improve RWS itinerary model (draw nodes/edges model) | 2011-01-18 | 2011-01-20 | 2011-01-20 | |
26 | Web app: Implement tabbing of locations in Flash user form (prototype) | 2011-01-21 | 2011-01-22 | 2011-01-21 | |
27 | Web app: Implement onClick feature for patrons to view location's information | 2011-01-20 | 2011-01-22 | 2011-01-21 | |
Week of 23 January 2011 to 29 January 2011 (SMU Week 4) | |||||
28 | Web app: Flash form (Activate all 7 dropboxes in customise itinerary page) | 2011-01-23 | 2011-01-26 | 2011-01-26 | |
29 | Web app: Flash form (Timebar to close empty time gaps and validate should a patron drop a variable into a box with a gap in front) | 2011-01-23 | 2011-01-26 | 2011-01-26 | |
30 | Web app: Flash form (update TimeBar function and create all 53 variable thumbnails to be added in Flash) | 2011-01-23 | 2011-01-26 | 2011-01-26 | |
31 | Web app: Flash form (allow patron to select preset itineraries - no choices input yet) | 2011-01-23 | 2011-01-26 | 2011-01-26 | |
32 | Web app: Flash form (create variables to be sent to ASP) | 2011-01-23 | 2011-01-26 | 2011-01-26 | |
33 | "Web app: Implement RWS algorithm in ASP.NET
a. Take user preference – calculate the no. of matches (priority points) in each location (Including starting location) |
2011-01-26 | 2011-01-27 | 2011-01-27 | |
34 | Deploy on UPL Server | 2011-01-28 | 2011-01-28 | 2011-01-28 | |
Week of 30 January 2011 to 05 February 2011 (SMU Week 5) | |||||
35 | Web app: Change planner ID to save patron's email address instead | 2011-01-29 | 2011-01-29 | 2011-01-29 | |
36 | Web app: Reflect Itinerary based on ASP.NET data (Send ASP/ Receive ASP/ Save Itinerary) | 2011-01-30 | 2011-02-01 | 2011-02-01 | |
37 | "Web app algo: Full RWS Algo (for 1 day of itinerary)
1. Ratings (check each location ratings – use formula of (preference/distance), need to update the two types of location lists – dining and non-dining dynamically) |
2011-01-30 | 2011-02-04 | 2011-02-04 | Modified algo to calculate user preferences on ratio instead of points |
38 | Web app: Receive user preference and details from flash, pass results (itinerary) – locationID, defaultDuration in arrayList | 2011-02-04 | 2011-02-05 | 2011-02-05 | |
Week of 06 February 2011 to 12 February 2011 (SMU Week 6) | |||||
39 | Web app: Validate Functions for UAT | 2011-02-06 | 2011-02-09 | 2011-02-09 | |
40 | Prepare for UAT with business users at RWS & SMU | 2011-02-06 | 2011-02-09 | 2011-02-09 | |
41 | Prepare for Mid Term Review (Slides) | 2011-02-06 | 2011-02-12 | 2011-02-16 | |
42 | Conduct and Review UAT to implement changes | 2011-02-10 | 2011-02-12 | 2011-02-12 | |
Week of 13 February 2011 to 19 February 2011 (SMU Week 7) | |||||
43 | Web app: Validate Functions for Mid Term Review 1. Add a Start button for patrons to click and start planning their itinerary" |
2011-02-13 | 2011-02-16 | 2011-02-16 | |
44 | Web app: Review Mid Term and Implement Changes | 2011-02-16 | 2011-02-19 | 2011-02-19 | |
Week of 20 February 2011 to 26 February 2011 (SMU Week 8) | |||||
45 | Web app: Improve RWS algo and tidy up UI to make it more sleek | 2011-02-20 | 2011-02-26 | 2011-02-26 | |
46 | Web app: Tidy up emailer that is being sent after patron creates his itinerary | 2011-02-24 | 2011-02-26 | 2011-02-26 | |
Week of 27 February 2011 to 05 March 2011 (SMU Week 9) | |||||
47 | Web app: Allow for more than 54 variables to be added | 2011-02-27 | 2011-03-05 | 2011-03-05 | |
48 | Convert RWS algo into ASP codes | 2011-02-27 | 2011-03-05 | 2011-03-05 | |
Week of 06 March 2011 to 12 March 2011 (SMU Week 10) | |||||
49 | Web app: YourSingapore time bar and accommodate for 3 days of itinerary planning | 2011-03-06 | 2011-03-23 | YourSingapore time bar task delayed as more research is needed | |
50 | Web app: Create UAT Test plan, survey forms and instructions | 2011-03-10 | 2011-03-12 | 2011-03-12 | |
Week of 13 March 2011 to 19 March 2011 (SMU Week 11) | |||||
51 | Web app: Show time dimensions | 2011-03-13 | 2011-03-19 | 2011-03-12 | Finished early; swap with task 69 |
52 | Update User Manual (Test Plan and Test Script) for web app, mobile and Mgmt | 2011-03-16 | 2011-03-19 | 2011-03-19 | |
Week of 27 March 2011 to 02 April 2011 (SMU Week 13) | |||||
53 | Web app: display correct dateTime format | 2011-03-27 | 2011-04-02 | 2011-04-02 | |
54 | Testing of algo and implement changes if any | 2011-04-01 | 2011-04-02 | 2011-04-02 | |
Week of 03 March 2011 to 09 April 2011 (SMU Week 14) | |||||
55 | Conduct UAT 2 with SMU peers and patrons at RWS | 2011-03-27 | 2011-03-30 | 2011-03-30 | |
56 | Create Test Reports and implement changes based on UAT 2 | 2011-03-31 | 2011-03-31 | 2011-03-31 |
Click here to go back to the Project Schedule page.