HeaderSIS.jpg

Pointers' Project Schedule

From IS480
Jump to navigation Jump to search
Legend
Task no. Description Planned Start Date Planned End Date Actual End Date Comments
Week of 29 November 2010 to 4 December 2010
1 Define Functionalities for Project Scope 2010-11-29 2010-11-29 2010-11-29
2 Set Milestones and Targetted Goals 2010-11-30 2010-11-30 2010-11-30
3 Create Project Management Gantt Chart 2010-12-01 2010-12-01 2010-12-01
4 Research mobile platforms (Android, iPhone and Mobile web application) 2010-12-02 2010-12-04 2010-12-04
Week of 05 December 2010 to 11 December 2010
5 Research ASP/Flash Connections for Intelligent Integrated Itinerary Planner (Web App) 2010-12-05 2010-12-07 2010-12-07 Start of Iteration 1
6 Specify Functionalities for Web app, Mobile web app, Management Portal 2010-12-08 2010-12-08 2010-12-08
7 Create Diagrams (Deployment, Solutions Architecture, ER, Use Case) 2010-12-09 2010-12-09 2010-12-09
8 Design User Interface for Web app, Mobile web app, Management Portal (Storyboard) 2010-12-09 2010-12-09 2010-12-09
9 Create MS SQL Create Data Schema 2010-12-09 2010-12-09 2010-12-09
10 Develop User Interface for Web app and Management Portal 2010-12-10 2010-12-10 2010-12-10
11 Design RWS Itinerary and USS Itinerary List View in Microsoft Powerpoint 2010-12-10 2010-12-10 2010-12-10
12 Develop algorithm for Web app and Mobile web app 2010-12-10 2010-12-10 2010-12-10
Week of 12 December 2010 to 18 December 2010
13 Develop Management Portal: CRUD Variables Information 2010-12-12 2010-12-13 2010-12-13
14 IIIP: Create User Form using Adobe Flash 2010-12-12 2010-12-14 2010-12-14
15 Develop Management Portal: CRD Attributes Information 2010-12-14 2010-12-15 2010-12-15
16 Develop RWS itinerary selection model in excel 2010-12-14 2010-12-17 2010-12-17
Week of 19 December 2010 to 25 December 2010
17 Develop Management Portal: CRUD Administrative Users 2010-12-19 2010-12-19 2010-12-19
18 IIIP: Implement RWS itinerary selection model using excel 2010-12-18 2010-12-22 2010-12-22
19 Implement display of RWS itinerary list view in ASP.NET 2010-12-23 2010-12-25 2010-12-25
20 Populate database with selection model attributes 2010-12-25 2010-12-25 2010-12-25
Week of 26 December 2010 to 01 January 2011
21 Test and Improve features in Management Portal for Project Acceptance Presentation 2010-12-26 2010-12-27 2010-12-27
22 Integrate Web app with excel database 2010-12-26 2010-12-27 2010-12-27
23 Improve User Interface of Flash user form for Project Acceptance Presentation 2010-12-29 2010-12-29 2010-12-29
24 Design Powerpoint slides for Project Acceptance Presentation 2010-12-29 2010-12-31 2010-12-31
25 Project Acceptance Presentation 2010-12-31 2010-12-31 2010-12-31 End of Iteration 1
Week of 02 January 2011 to 08 January 2011 (SMU Week 1)
26 Allow Management Portal users to input the weather manually (sunny/rainy) 2011-01-04 2011-01-05 2011-01-05 Start of Iteration 2
27 Create Connection between ASP and Flash (prototype) 2011-01-04 2011-01-06 2011-01-06
28 Improve User Interface for Flash User Form 2011-01-06 2011-01-08 2011-01-08
29 Research and create prototype of drag-and-drop feature (customise itinerary) 2011-01-06 2011-01-08 2011-01-08
30 Create buttons in Management Portal to directly update details of locations 2011-01-06 2011-01-07 2011-01-07
31 Allow Management Portal users to update attribute values via a table display 2011-01-07 2011-01-08 2011-01-08
32 Implemented Smart Traveller detecting web browser used by smartphone 2011-01-07 2011-01-08 2011-01-08
Week of 09 January 2011 to 15 January 2011 (SMU Week 2)
33 Management Portal: Validation and Testing for all functions 2011-01-09 2011-01-12 2011-01-12
34 Web app: WebApp on localhost, timeline, drag&drop feature integrated (prototype) 2011-01-09 2011-01-11 2011-01-11
35 Mobile web app: Create user form to enter planner ID and link to MS SQL database 2011-01-10 2011-01-11 2011-01-11
36 Mobile web app: Display static itinerary list 2011-01-11 2011-01-12 2011-01-12
37 Mobile web app: Implement check/uncheck feature for USS itinerary 2011-01-13 2011-01-14 2011-01-14
38 Web app: Allow for double-click to edit duration when customising itinerary 2011-01-12 2011-01-14 2011-01-21 onClick to view edit duration at bottom of page
39 Web app: Develop timeline to allow it to be is smart enough to fill in empty gaps 2011-01-12 2011-01-14 2011-01-14
Week of 16 January 2011 to 22 January 2011 (SMU Week 3)
40 Web app: WebApp on localhost, timeline, drag&drop feature integrated 2011-01-16 2011-01-18 2011-01-28 Server not up yet, will be deployed next Tuesday
41 Improve RWS itinerary model (draw nodes/edges model) 2011-01-18 2011-01-20 2011-01-20
42 Web app: Implement tabbing of locations in Flash user form (prototype) 2011-01-21 2011-01-22 2011-01-21
43 Mobile web app: Display itinerary based on Planner ID 2011-01-16 2011-01-19 2011-01-19
44 Web app: Implement onClick feature for patrons to view location's information 2011-01-20 2011-01-22 2011-01-21
Week of 23 January 2011 to 29 January 2011 (SMU Week 4)
45 Web app - Update UI 2011-01-23 2011-01-26 2011-01-26
46 Web app: Implement RWS algorithm in ASP.NET 2011-01-27 2011-01-29 2011-01-29
47 Mobile web app: Update UI (Image Link Works, Font size changed, template for gridview and
background color changed, logo added)
2011-01-27 2011-01-29 2011-01-29
Week of 30 January 2011 to 05 February 2011 (SMU Week 5)
48 Web app: Reflect Itinerary based on ASP.NET data (Send ASP/ Receive ASP/ Save Itinerary) 2011-01-30 2011-02-01 2011-02-01
49 Web app: Full RWS Algo 2011-01-30 2011-02-03 2011-02-03
50 Mobile web app: Show RWS itinerary 2011-01-30 2011-02-03 2011-02-03
51 Web app algo: Take in Ratings and Operating Hours 2011-01-30 2011-02-01 2011-02-01
52 Web app: Receive user preference and details from flash, pass results (itinerary) – locationID,
defaultDuration in arrayList
2011-02-02 2011-02-05 2011-02-05
Week of 06 February 2011 to 12 February 2011 (SMU Week 6)
53 Web app and Mobile web app: Validate Functions for UAT 2011-02-06 2011-02-09
54 Prepare for Mid Term Review (Slides) 2011-02-06 2011-02-12 2011-02-12
55 Prepare for UAT with business users at RWS 2011-02-06 2011-02-09 2011-02-09 Deployment on 8th Feb at RWS
56 Conduct and Review UAT to implement changes 2011-02-10 2011-02-12 2011-02-12
Week of 13 February 2011 to 19 February 2011 (SMU Week 7)
57 Web app and Mobile web app: Validate Functions for Mid Term Review 2011-02-13 2011-02-16 2011-02-16
58 Prepare for Mid Term Review (Slides and Rehearsal) 2011-02-13 2011-02-16 2011-02-16
59 Mid Term Review Presentation 2011-02-16 2011-02-16 2011-02-16
60 Review Mid Term and Implement Changes 2011-02-16 2011-02-19 2011-02-19
Week of 20 February 2011 to 26 February 2011 (SMU Week 8)
61 Web app: Improve RWS algo and tidy up UI 2011-02-20 2011-02-26 2011-02-26
62 Mobile web app: Implement USS selection model and algorithm 2011-02-20 2011-02-26 2011-02-26
63 Mobile web app: Update the database to include USS variables 2011-02-24 2011-02-26 2011-02-26
64 Web app: Tidy up emailer 2011-02-24 2011-02-26 2011-02-26
Week of 27 February 2011 to 05 March 2011 (SMU Week 9)
65 Web app: Allow for more than 54 variables to be added 2011-02-27 2011-03-05 2011-03-05
66 Web app: Convert algo into ASP codes 2011-02-27 2011-03-05 2011-03-05
67 Mobile web app: Improve the UI and design USS pages 2011-02-27 2011-03-05 2011-03-05
68 Mobile web app: Implement Facebook like and share features 2011-02-27 2011-03-05 2011-03-05
Week of 06 March 2011 to 12 March 2011 (SMU Week 10)
69 Web app: YourSingapore time bar and accommodate for 3 days of itinerary planning 2011-03-06 2011-03-12 2011-03-12 More research required for YourSingapore time bar
70 Mobile web app: Convert USS algo into ASP codes 2011-03-06 2011-03-12 2011-03-12
71 Mobile web app: Integrate HTML UI to back-end ASP codes 2011-03-06 2011-03-12 2011-03-12 Need to modify back-end to suit mobile UI
72 Mobile web app: ALL: Create UAT Test plan, survey forms and instructions 2011-03-10 2011-03-12 2011-03-12
Week of 13 March 2011 to 19 March 2011 (SMU Week 11)
73 Web app: Show time dimensions 2011-03-13 2011-03-19 2011-03-12 Finished early; swap with task 69
74 Mobile web app: Create instructions page 2011-03-13 2011-03-15 2011-03-15
75 ALL: Update User Manual (Test Plan and Test Script) for web app, mobile and Mgmt 2011-03-16 2011-03-19 2011-03-19
Week of 20 March 2011 to 26 March 2011 (SMU Week 12)
76 Web app & Mobile web app: Testing of algo and implement changes if any 2011-03-20 2011-03-22 2011-03-29
77 Management Portal: Implement USS Update Waiting Time & Allow add and delete 2011-03-23 2011-03-26 2011-04-01
78 Design Poster for submission 2011-03-23 2011-03-26 2011-03-26
Week of 27 March 2011 to 02 April 2011 (SMU Week 13)
79 Conduct UAT 2 with SMU peers and patrons at RWS 2011-03-27 2011-03-30 2011-03-30
80 Create Test Reports based on UAT 2 2011-03-31 2011-03-31 2011-03-31
81 Web app & Mobile web app: display correct dateTime format 2011-03-27 2011-04-02
82 Web app & Mobile web app: Testing of algo and implement changes if any 2011-04-01 2011-04-02
83 Management Portal: Update according to new database structure 2011-04-01 2011-04-02
84 ALL: Add print screens to UAT Plan 2011-04-01 2011-04-02
85 Prepare Presentation slides and video 2011-04-01 2011-04-02
Week of 03 April 2011 to 09 April 2011 (SMU Week 14)
86 Conduct UAT 2 with SMU peers and patrons at RWS 2011-04-02 2011-04-04
87 Create Test Reports and implement changes (if any) based on UAT 2 2011-04-05 2011-04-05
Week of 10 April 2011 to 16 April 2011 (SMU Week 15)
88 Rehearsal for Presentation and Prepare demonstration 2011-04-13 2011-04-14
89 ALL: Handover to RWS/stakeholders 2011-04-14 2011-04-14
90 Final Presentation 2011-04-15 2011-04-15
Week of 17 April 2011 to 23 April 2011 (SMU Week 16)
91 Submission of Documentation/Poster Day 2011-04-20 2011-04-20



Click here to go back to main page.