Week of 29 November 2010 to 4 December 2010
1 Define Functionalities for Project Scope 2010-11-29 2010-11-29 2010-11-29
2 Set Milestones and Targetted Goals 2010-11-30 2010-11-30 2010-11-30
3 Create Project Management Gantt Chart 2010-12-01 2010-12-01 2010-12-01
4 Research mobile platforms (Android, iPhone and Mobile web application) 2010-12-02 2010-12-04 2010-12-04
Week of 05 December 2010 to 11 December 2010
5 Research ASP/Flash Connections for Intelligent Integrated Itinerary Planner (Web App) 2010-12-05 2010-12-07 2010-12-07 Start of Iteration 1
6 Specify Functionalities for Web app, Mobile web app, Management Portal 2010-12-08 2010-12-08 2010-12-08
7 Create Diagrams (Deployment, Solutions Architecture, ER, Use Case) 2010-12-09 2010-12-09 2010-12-09
8 Design User Interface for Web app, Mobile web app, Management Portal (Storyboard) 2010-12-09 2010-12-09 2010-12-09
9 Create MS SQL Create Data Schema 2010-12-09 2010-12-09 2010-12-09
10 Develop User Interface for Web app and Management Portal 2010-12-10 2010-12-10 2010-12-10
11 Design RWS Itinerary and USS Itinerary List View in Microsoft Powerpoint 2010-12-10 2010-12-10 2010-12-10
12 Develop algorithm for Web app and Mobile web app 2010-12-10 2010-12-10 2010-12-10
Week of 12 December 2010 to 18 December 2010
13 Develop Management Portal: CRUD Variables Information 2010-12-12 2010-12-13 2010-12-13
14 IIIP: Create User Form using Adobe Flash 2010-12-12 2010-12-14 2010-12-14
15 Develop Management Portal: CRD Attributes Information 2010-12-14 2010-12-15 2010-12-15
16 Develop RWS itinerary selection model in excel 2010-12-14 2010-12-17 2010-12-17
Week of 19 December 2010 to 25 December 2010
17 Develop Management Portal: CRUD Administrative Users 2010-12-19 2010-12-19 2010-12-19
18 IIIP: Implement RWS itinerary selection model using excel 2010-12-18 2010-12-22 2010-12-22
19 Implement display of RWS itinerary list view in ASP.NET 2010-12-23 2010-12-25 2010-12-25
20 Populate database with selection model attributes 2010-12-25 2010-12-25 2010-12-25
Week of 26 December 2010 to 01 January 2011
21 Test and Improve features in Management Portal for Project Acceptance Presentation 2010-12-26 2010-12-27 2010-12-27
22 Integrate Web app with excel database 2010-12-26 2010-12-27 2010-12-27
23 Improve User Interface of Flash user form for Project Acceptance Presentation 2010-12-29 2010-12-29 2010-12-29
24 Design Powerpoint slides for Project Acceptance Presentation 2010-12-29 2010-12-31 2010-12-31
25 Project Acceptance Presentation 2010-12-31 2010-12-31 2010-12-31 End of Iteration 1
Week of 02 January 2011 to 08 January 2011 (SMU Week 1)
26 Allow Management Portal users to input the weather manually (sunny/rainy) 2011-01-04 2011-01-05 2011-01-05 Start of Iteration 2
27 Create Connection between ASP and Flash (prototype) 2011-01-04 2011-01-06 2011-01-06
28 Improve User Interface for Flash User Form 2011-01-06 2011-01-08 2011-01-08
29 Research and create prototype of drag-and-drop feature (customise itinerary) 2011-01-06 2011-01-08 2011-01-08
30 Create buttons in Management Portal to directly update details of locations 2011-01-06 2011-01-07 2011-01-07
31 Allow Management Portal users to update attribute values via a table display 2011-01-07 2011-01-08 2011-01-08
32 Implemented Smart Traveller detecting web browser used by smartphone 2011-01-07 2011-01-08 2011-01-08
Week of 09 January 2011 to 15 January 2011 (SMU Week 2)
33 Management Portal: Validation and Testing for all functions 2011-01-09 2011-01-12 2011-01-12
34 Web app: WebApp on localhost, timeline, drag&drop feature integrated (prototype) 2011-01-09 2011-01-11 2011-01-11
35 Mobile web app: Create user form to enter planner ID and link to MS SQL database 2011-01-10 2011-01-11 2011-01-11
36 Mobile web app: Display static itinerary list 2011-01-11 2011-01-12 2011-01-12
37 Mobile web app: Implement check/uncheck feature for USS itinerary 2011-01-13 2011-01-14 2011-01-14
38 Web app: Allow for double-click to edit duration when customising itinerary 2011-01-12 2011-01-14
39 Web app: Develop timeline to allow it to be is smart enough to fill in empty gaps 2011-01-12 2011-01-14 2011-01-14
Week of 16 January 2011 to 22 January 2011 (SMU Week 3)
40 Web app: WebApp on localhost, timeline, drag&drop feature integrated 2011-01-16 2011-01-18
41 Web app: Implement tabbing of locations in Flash user form 2011-01-18 2011-01-20
42 Web app: Implement onClick feature for patrons to view location's information 2011-01-21 2011-01-22
43 Mobile web app: Improve interfaces (login, list views, checking feature pages) 2011-01-16 2011-01-19
44 Improve RWS itinerary model (need to take in Users' Ratings) 2011-01-20 2011-01-22
Week of 23 January 2011 to 29 January 2011 (SMU Week 4)
45 Web app: Implement RWS Itinerary selection model in ASP.NET 2011-01-23 2011-01-26
46 Web app: Implement tabbing of locations in Flash user form 2011-01-27 2011-01-29
47 Web app: Implement onClick feature for patrons to view location's information 2011-01-27 2011-01-29
Week of 30 January 2011 to 05 February 2011 (SMU Week 5)
48 Web app: Implement RWS itinerary algorithm based on distance between variables 2011-01-30 2011-02-01
49 Web app: Implement RWS itinerary algorithm based on operating hours 2011-02-02 2011-02-05
Week of 06 February 2011 to 12 February 2011 (SMU Week 6)
50 Web app and Mobile web app: Validate Functions for UAT 2011-02-06 2011-02-09
51 Prepare for UAT with business users at RWS 2011-02-06 2011-02-09
52 Review UAT and Implement Changes 2011-02-10 2011-02-12
Week of 13 February 2011 to 19 February 2011 (SMU Week 7)
53 Web app and Mobile web app: Validate Functions for Mid Term Review 2011-02-13 2011-02-16
54 Prepare for Mid Term Review 2011-02-13 2011-02-16
55 Mid Term Review Presentation 2011-02-16 2011-02-16
56 Review Mid Term and Implement Changes 2011-02-16 2011-02-19 End of Iteration 2
Week of 20 February 2011 to 26 February 2011 (SMU Week 8)
57 Mobile web app: Implement USS itinerary model 2011-02-20 2011-02-23
58 Mobile web app: Implement USS algorithm 2011-02-24 2011-02-26
59 Mobile web app: Implement Facebook plug-in for sharing and liking of RWS 2011-02-20 2011-02-23
60 Mobile web app: Implement feature to allow patrons to "like" the locations 2011-02-24 2011-02-26
Week of 27 February 2011 to 05 March 2011 (SMU Week 9)
61 Integration of all functions (Web app, Mobile web app and Management Portal) 2011-02-27 2011-03-05
Week of 06 March 2011 to 12 March 2011 (SMU Week 10)
62 Project Buffer or Create user form on mobile web app 2011-03-06 2011-03-12
Week of 13 March 2011 to 19 March 2011 (SMU Week 11)
63 Create User Manual (Test Plan and Test Script) for web app, mobile and Mgmt 2011-03-13 2011-03-16
64 Conduct UAT 2 with SMU peers and patrons at RWS 2011-03-17 2011-03-19
Week of 20 March 2011 to 26 March 2011 (SMU Week 12)
65 Create Test Reports based on UAT 2 2011-03-20 2011-03-21
66 Implement changes based on UAT 2 2011-03-22 2011-03-26
67 Design Poster for submission 2011-03-24 2011-03-26
Week of 27 March 2011 to 02 April 2011 (SMU Week 13)
68 Submit Poster 2011-03-28 2011-03-28
69 Write Report 2011-03-28 2011-04-02
Week of 03 April 2011 to 09 April 2011 (SMU Week 14)
70 Prepare Demostration 2011-03-03 2011-03-06
71 Prepare Presentation slides and Flow 2011-03-07 2011-03-09
Week of 10 April 2011 to 16 April 2011 (SMU Week 15)
72 Rehearsal for Presentation 2011-03-10 2011-03-16
Week of 03 April 2011 to 09 April 2011 (SMU Week 14)
73 Final Presentation 2011-03-17 2011-03-17
74 Submission of Documentation 2011-03-17 2011-03-17