Current Schedule

Overall

Burndown Chart

Individual Sprints

Click on the charts to see the task lists and detailed progress!

Sprint 0

to view the Sprint tracking and tasksLogiciel Sprint 0 Burndown.png

Task List:

S/N Tasks Planned Completed Completed %
1 Login 5 5 100%
2 Interface - Search Form 10 10 100%
3 Interface - Search Results 10 10 100%
4 Interface - Top Factor Graphs 10 10 100%
Total 35 35 100%

Sprint 1

to view the Sprint tracking and tasksLogiciel Sprint 1 Burndown.png

Task List:

S/N Tasks Planned Completed Completed %
Perform Search
1 Setup and configure Apache Solr 5 5 100%
2 Enable full-text search on app server 10 10 100%
3 Integrate app server with interface 5 5 100%
4 Create page for advanced Search 15 0 0%
Graph - Regional Win/Loss
5 Draw D3 clickable pie chart 6 6 100%
6 Create drilldown pages 6 0 0%
7 Read graph data from server 3 2 67%
Graph - Top Factor(redo)
8 Draw D3 stacked bar chart 6 6 100%
9 Create drilldown pages 6 0 0%
10 Read graph data from server 3 2 67%
Total 65 36 55%
  • Orange tasks are carried over from last sprint. The darker it is, the more times it has been carried over.

Sprint 2

to view the Sprint tracking and tasksLogiciel Sprint 2 Burndown.png
S/N Tasks Planned Completed Completed %
1 Create page for advanced Search 15 15 100%
Graph - Regional Win/Loss
2 Create drilldown pages (Location) 6 1.5 25%
3 Read graph data from server 1 1 100%
Graph - Top Factor
4 Create drilldown pages (Factor) 6 3.5 58%
5 Read graph data from server 1 0 0%
Graph - Sales Team Perf
6 Draw D3 scatterplot 6 6 100%
7 Create drilldown pages (Deal Owner) 6 3 50%
8 Read graph data from server 3 3 100%
Graph - Win & Loss Competitors
9 Draw D3 line chart 6 0 0%
10 Create drilldown pages (Competitor) 6 0 0%
11 Read graph data from server 3 0 0%
Total 59 33 56%
  • Orange tasks are carried over from last sprint. The darker it is, the more times it has been carried over.

Sprint 3

to view the Sprint tracking and tasksLogiciel Sprint 3 Burndown.png

Sprint 4

to view the Sprint tracking and tasksLogiciel Sprint 4 Burndown.png

Sprint 5

Sprint 6

Sprint 7

Sprint 8

Sprint 9