Difference between revisions of "Logiciel Project Management"
Jump to navigation
Jump to search
Line 142: | Line 142: | ||
desc none | desc none | ||
</imagemap> | </imagemap> | ||
− | + | ===Task List:=== | |
{| {{table}} | {| {{table}} | ||
| align="center" style="background:#f0f0f0;"|'''S/N''' | | align="center" style="background:#f0f0f0;"|'''S/N''' |
Revision as of 01:24, 2 February 2013
Contents
Current Schedule
Overall
Burndown Chart
Individual Sprints
Click on the charts to see the task lists and detailed progress!
Sprint 0
Task List:
S/N | Tasks | Planned | Completed | Completed % |
1 | Login | 5 | 5 | 100% |
2 | Interface - Search Form | 10 | 10 | 100% |
3 | Interface - Search Results | 10 | 10 | 100% |
4 | Interface - Top Factor Graphs | 10 | 10 | 100% |
Total | 35 | 35 | 100% | |
Sprint 1
Task List:
S/N | Tasks | Planned | Completed | Completed % |
Graph - Top Factor(redo) | ||||
1 | Draw D3 stacked bar chart | 6 | 6 | 100% |
2 | Create drilldown pages | 6 | 0 | 0% |
3 | Read graph data from server | 3 | 2 | 67% |
Perform Search | ||||
4 | Setup and configure Apache Solr | 5 | 5 | 100% |
5 | Enable full-text search on app server | 10 | 10 | 100% |
6 | Integrate app server with interface | 5 | 5 | 100% |
7 | Create page for advanced Search | 15 | 0 | 0% |
Graph - Regional Win/Loss | ||||
8 | Draw D3 clickable pie chart | 6 | 6 | 100% |
9 | Create drilldown pages | 6 | 0 | 0% |
10 | Read graph data from server | 3 | 2 | 67% |
Total | 65 | 36 | 55% | |
- Peach-colored tasks are tasks that were carried over from last sprint. The darker it is, the more times it has been carried over.
Sprint 2
Task List:
S/N | Tasks | Planned | Completed | Completed % |
1 | Create page for advanced Search | 15 | 15 | 100% |
Graph - Regional Win/Loss | ||||
2 | Create drilldown pages (Location) | 6 | 1.5 | 25% |
3 | Read graph data from server | 1 | 1 | 100% |
Graph - Top Factor | ||||
4 | Create drilldown pages (Factor) | 6 | 3.5 | 58% |
5 | Read graph data from server | 1 | 0 | 0% |
Graph - Sales Team Perf | ||||
6 | Draw D3 scatterplot | 6 | 6 | 100% |
7 | Create drilldown pages (Deal Owner) | 6 | 3 | 50% |
8 | Read graph data from server | 3 | 3 | 100% |
Graph - Win & Loss Competitors | ||||
9 | Draw D3 line chart | 6 | 0 | 0% |
10 | Create drilldown pages (Competitor) | 6 | 0 | 0% |
11 | Read graph data from server | 3 | 0 | 0% |
Total | 59 | 33 | 56% |
- Peach-colored tasks are tasks that were carried over from last sprint. The darker it is, the more times it has been carried over.
Sprint 3
The deliverables shown here are those that have been re-planned. A lot of work was getting carried over to the next sprint and we needed to get a realistic view of the schedule. Other than Export Results, all other tasks are tasks that were initially planned to be completed before this sprint.
Task List:
S/N | Tasks | Planned | Completed | Completed % |
Graph - Regional Win/Loss | ||||
1 | Create drilldown pages (Location) | 7.5 | 5.5 | 73% |
Graph - Top Factor | ||||
2 | Create drilldown pages (Factor) | 5.5 | 4.5 | 82% |
3 | Read graph data from server | 1 | 1 | 100% |
Graph - Sales Team Perf | ||||
4 | Create drilldown pages (Deal Owner) | 6 | 3 | 50% |
Graph - Trending Competitors | ||||
5 | Draw D3 line chart | 9 | 6 | 67% |
6 | Read graph data from server | 3 | 0% | |
7 | Export Results | 10 | 0% | |
Total | 42 | 20 | 48% | |
Sprint 4
Task List:
S/N | Tasks | Planned | Completed | Completed % |
Graph - Regional Win/Loss | ||||
1 | Create detail pages (Location) | 2 | 0 | 0% |
Graph - Top Factor | ||||
2 | Create detail pages (Factor) | 1 | 0 | 0% |
Graph - Trending Competitors | ||||
3 | Draw D3 line chart | 3 | 3 | 100% |
4 | Read graph data from server | 3 | 2 | 67% |
Graph - Sales Team Perf | ||||
5 | Create detail pages (Deal Owner) | 6 | 6 | 100% |
6 | Export Results | 10 | 8 | 80% |
7 | Create detail pages (Competitor) | 9 | 0 | 0% |
Graph - Loss Competitors | ||||
8 | Draw D3 loss bar chart | 9 | 0 | 0% |
9 | Read graph data from server | 3 | 0 | 0% |
Graph - Product Total Revenue | ||||
10 | Draw D3 negative bar chart | 9 | 9 | 100% |
11 | Create detail pages (Product) | 9 | 9 | 100% |
12 | Read graph data from server | 3 | 3 | 100% |
Total | 67 | 40 | 60% | |
- Peach-colored tasks are tasks that were carried over from last sprint. The darker it is, the more times it has been carried over.