This is Kopa Wheel Project Schedule
Legend: | |
Milestones | Milestones |
Progress | Task in Progress |
Completed | Task Completed |
S/N | Description | Planned Start Date | Planned End Date | Actual Start Date | Actual End Date | Progress Status | In-Charge | Remarks |
---|---|---|---|---|---|---|---|---|
Iteration 2: 15/8/2011 to 26/8/2011 (10 Days) | ||||||||
Dashboard | ||||||||
1 | Year on Year Changes of 6 CSISG Indices (Horizontal Bar Chart) | 17/8/2011 | 17/8/2011 | 17/8/2011 | 28/8/2011 | Completed | Feixiang | Enhanced: Standardised to Joomla |
2 | Multiple Years Selection for the 6 CSISG Indices (Line Chart) | 18/8/2011 | 18/8/2011 | 18/8/2011 | 28/8/2011 | Completed | Feixiang | Enhanced: Standardised to Joomla |
3 | View Benchmarking Line Chart | 18/8/2011 | 18/8/2011 | 18/8/2011 | 28/8/2011 | Completed | Feixiang | - |
4 | Performance vs Impact Chart | 18/8/2011 | 18/8/2011 | 18/8/2011 | 28/8/2011 | Completed | Feixiang | New Requirement |
Explorer Tool | ||||||||
5 | View Charts pertaining to all Questions (Vertical Bar Charts) | 17/8/2011 | 19/8/2011 | 17/8/2011 | 19/8/2011 | - | James | New Change has been introduced |
6 | View Charts pertaining to all Questions (Confidence Interval Charts) | 19/8/2011 | 28/8/2011 | 26/8/2011 | 28/8/2011 | Completed | James | New Requirement |
7 | View Charts pertaining to all Questions (Vertical Bar Charts - Statistics of Respondants) | 22/8/2011 | 28/8/2011 | 26/8/2011 | 28/8/2011 | Completed | James | - |
8 | Allow Drill Down of Charts by Demographics (Vertical Bar Charts) | 22/8/2011 | 24/8/2011 | - | - | - | James | Requirements Removed by Client |
User Interface Design | ||||||||
9 | Design a template for the CSISG web portal | 17/8/2011 | 24/8/2011 | 17/8/2011 | 28/8/2011 | Completed | James | Still ongoing for enhanced Improvements |
10 | Dynamically call R Script from PHP Apache for all the charts | 24/8/2011 | 24/9/2011 | 24/8/2011 | In Progress | Lianghua | - | |
Iteration 3: 01/9/2011 to 15/9/2011 (9 Days) | ||||||||
Reporting | ||||||||
11 | Organize added reports in Report Organizer | 01/9/2011 | 06/9/2011 | 01/9/2011 | In Progress | James/Lianghua | - | |
12 | Export Charts into PDF format | 07/9/2011 | 12/9/2011 | Not Started | Lianghua | Delayed | ||
Administration | ||||||||
13 | Create User Interface to allow Admins to Create Subscription for a Corporate User | 01/9/2011 | 09/9/2011 | 01/9/2011 | 09/9/2011 | Completed | Yuting/James | Some more slight Changes to be made for Admin Function |
Model Builder | ||||||||
14 | Create the User Interface for Admin to key in inputs | 01/9/2011 | 05/9/2011 | 01/9/2011 | 05/9/2011 | Completed | James/Feixiang | - |
15 | Build the Model Builder in Dot Language | 06/9/2011 | 10/9/2011 | 06/9/2011 | 10/9/2011 | Completed | James | - |
16 | Storing Values of the Model into Database | 06/9/2011 | 10/9/2011 | 06/9/2011 | 10/9/2011 | Completed | Feixiang | - |
17 | Apply the Model Built by the Admin in the Explorer Tool | 10/9/2011 | 12/9/2011 | 10/9/2011 | 12/9/2011 | Completed | James | - |
UAT Preparations | ||||||||
18 | Prepare UAT | 14/9/2011 | 18/9/2011 | 14/9/2011 | In Progress | Yuting | - | |
Milestone: UAT 1 (20/09/2011 to 21/09/2011) | ||||||||
19 | Prepare Midterm Presentation | 14/9/2011 | 30/9/2011 | 14/9/2011 | In Progress | Yuting | - | |
19 | Making Changes based on UAT Feedback | 20/9/2011 | 26/9/2011 | Not Started | Everyone | - | ||
Milestone: Midterm Presentation (30/09/2011 4:30pm) | ||||||||
Iteration 4: 03/10/2011 to 13/10/2011 (10 Days) | ||||||||
Predictive Analysis | ||||||||
20 | Create Performance Impact Chart for Predictive Analysis | 03/10/2011 | 11/10/2011 | Not Started | - | |||
Iteration 5: 14/10/2011 to 28/10/2011 (14 Days) | ||||||||
Chart Builder | ||||||||
21 | Create a Chart Builder for Users to customize their own Chart | 14/10/2011 | 25/10/2011 | Not Started | - | |||
Archive of Reports | ||||||||
22 | Create a Archive of Reports to allow users to access old reports conveniently | 14/10/2011 | 25/10/2011 | Not Started | - | |||
FAQ | ||||||||
23 | Create FAQ to guide corporate clients on how to use the online portal | 14/10/2011 | 18/10/2011 | Not Started | - | |||
Milestone: UAT 2 (1/11/2011 to 2/11/2011) | ||||||||
Milestone: Poster Day Submission (7/11/2011) | ||||||||
Milestone: Final Presentation (21/11/2011) | ||||||||
Milestone: Final Submission (27/11/2011) |