Kopa Wheel Project Schedule
Revision as of 20:25, 31 August 2011 by Yuting.wee.2008 (talk | contribs)
This is Kopa Wheel Project Schedule
Legend: | |
Milestones | Milestones |
Start | Start of Iterations |
End | End of Iterations |
Progress | Task in Progress |
Completed | Task Completed |
S/N | Description | Planned Start Date | Planned End Date | Actual Start Date | Actual End Date | Progress Status | In-Charge | Remarks |
---|---|---|---|---|---|---|---|---|
Iteration 2: 15/8/2011 to 26/8/2011 (10 Days) | ||||||||
Dashboard | ||||||||
Year on Year Changes of 6 CSISG Indices (Horizontal Bar Chart) | 17/8/2011 | 17/8/2011 | In Progress | Feixiang | - | |||
Multiple Years Selection for the 6 CSISG Indices (Line Chart) | 18/8/2011 | 18/8/2011 | In Progress | Feixiang | - | |||
View Benchmarking Line Chart | 18/8/2011 | 18/8/2011 | In Progress | Feixiang | - | |||
Explorer Tool | ||||||||
View Charts pertaining to all Questions (Vertical Bar Charts) | 17/8/2011 | 19/8/2011 | - | James | Extended due to Change in Requirements | |||
View Charts pertaining to all Questions (Confidence Interval Charts + Vertical Bar Charts) | 26/8/2011 | 31/8/2011 | In Progress | James | Extended due to Change in Requirements | |||
Drill Down of Charts by Demographics (Vertical Bar Charts) | 22/8/2011 | 24/8/2011 | - | James | Requirements Removed by Client | |||
User Interface Design | ||||||||
Design a template for the CSISG web portal | 17/8/2011 | 24/8/2011 | 17/8/2011 | In Progress | Nicole | |||
Iteration 3: 01/9/2011 to 15/9/2011 (11 Days) | ||||||||
Reporting | ||||||||
Organize added reports in Report Organizer | 01/9/2011 | 06/9/2011 | Not Started | - | ||||
Export Charts into PDF format | 07/9/2011 | 09/9/2011 | Not Started | - | ||||
Administration | ||||||||
Create User Interface to allow Admins to Create Subscription for a Corporate User | Not Started | - | ||||||
Model Builder | ||||||||
Create the User Interface for Admin to key in inputs | Not Started | - | ||||||
Build the Model Builder in Dot Language | Not Started | - | ||||||
Apply the Model Built by the Admin in the Explorer Tool | Not Started | - | ||||||
UAT Preparations | ||||||||
Prepare UAT | Not Started | - | ||||||
Milestone: Midterm Presentation | ||||||||
Iteration 4: 03/10/2011 to 13/10/2011 (10 Days) | ||||||||
Predictive Analysis | ||||||||
Review Database Design | Not Started | - | ||||||
Create Performance Impact Chart for Predictive Analysis | Not Started | - | ||||||
Iteration 5: 14/10/2011 to 28/10/2011 (12 Days) | ||||||||
Chart Builder | ||||||||
Create a Chart Builder for Users to customize their own Chart | Not Started | - | ||||||
Archive of Reports | ||||||||
Create a Archive of Reports to allow users to access old reports conveniently | Not Started | - | ||||||
FAQ | ||||||||
Create FAQ to guide corporate clients on how to use the online portal | Not Started | - |