S/N | Description | Planned Start Date | Planned End Date | Actual Start Date | Actual End Date | Progress Status | In-Charge | Remarks |
---|---|---|---|---|---|---|---|---|
Iteration 2: 15/8/2011 to 26/8/2011 (10 Days) | ||||||||
Dashboard | ||||||||
1 | Year on Year Changes of 6 CSISG Indices | 17/8/2011 | 17/8/2011 | In Progress | Feixiang | - | ||
2 | Multiple Years Selection for the 6 CSISG Indices | 18/8/2011 | 18/8/2011 | In Progress | Feixiang | - | ||
3 | View Benchmarking Line Chart | 18/8/2011 | 18/8/2011 | In Progress | Feixiang | - | ||
Explorer Tool | ||||||||
4 | View Charts pertaining to all Questions | 17/8/2011 | 19/8/2011 | In Progress | James | - | ||
5 | Drill Down of Charts by Demographics | 22/8/2011 | 24/8/2011 | - | James | Requirements Removed by Client | ||
User Interface Design | ||||||||
6 | Design a template for the CSISG web portal | 17/8/2011 | 24/8/2011 | In Progress | Nicole | - | ||
Database Design | ||||||||
7 | Plan & Create a Database Design | 18/8/2011 | 24/8/2011 | In Progress | Feixiang | - |