Revision as of 14:59, 20 February 2009 by Yndivadkar.2006 (talk | contribs) (New page: Progress Report: Week 6 ==Things being done in week 6 (08/02/09-14/02/09):== • User Interface for Iteration 1 completed. • Bugs Testing for Iteration 1. • Pdf Generation integrat...)
Progress Report: Week 6
Contents
Things being done in week 6 (08/02/09-14/02/09):
• User Interface for Iteration 1 completed.
• Bugs Testing for Iteration 1.
• Pdf Generation integrated with the workflow
Highlights of Supervisor Meeting on 11th of February
-Update on tracking of bugs using a bug tracker
- Changing the interface for UAT
- Build a tool to change the workflow
- Users don’t read user manuals; Build a self explanatory user interface
- Mid term Project Reflection
- Risks Assesment
Our internal meetings schedule for academic weeks 4 and 5:
Tuesday, 10th February 1530 hrs to 1900 hrs
Wednesday, 11th February 1630 hrs to 1830 hrs
Proposed meeting schedule for Week 7
Monday, 16th February 1000hrs-1500 hrs
Wednesday, 18th February 1000 hrs to 1900 hrs
Work allocation for week 7 (08/02/09-14/02/09):
- Updated on Gantt Chart