IS480 Team wiki: DYMSZ Mid-Term
ABOUT US |
MID-TERM |
Contents
DYMSZ Project Progress Summary
- Till date of 27th Feb 2015, we have completed all our Primary and Secondary Functions
- Next Iteration starts on 27th Feb 2015 and ends on 13th Mar 2015 [It's when we will work on our Tertiary Function (Software Module)]
MileStone Completed
- Proposal Submission
- Acceptance
- UAT-1
- UAT-2
MileStone Completed
- Mid-Terms Presentation
- UAT-3
- Poster Submission
- Final Presentation
- Poster Day
Changes in Scope
Project Highlights
- Conducted a User Testing for 25 users to get general feedback of Android Application
- Conducted a focus group testing for 5 users to get more specific feedback on improvements to Android Application
- All iterations from Iteration 1 to 8 completed within projected schedule time so far
- Steep Learning Curve for Android Application technology and Integration between web portal and android application as well