Finals Wiki



Stage Specification Modules
Project Management Meeting Minutes Moments Minutes
Backlog Moments Backlogs
Burndown Charts Moments Charts
Diagrams Use Case & ER Diagrams Moments Diagrams
Testing UAT 2 & 3 UT2 | UT3
Prototype Paper Prototype Moments Paper Prototype
Presentation Slides Final Final Presentation


Moments header progress.png
No. Function Status Confidence Remarks
1. Account Management Module Fully deployed and tested 100% 1 Done
2. Vendor Module Fully deployed and tested 100% 1 Done
3. Customer Module Fully deployed and tested 100% 1 Done
4. Booking Module Fully deployed and tested 100% 1 Done
5. Event Module Fully deployed and tested 100% 1 Done
6. Payment Module Fully deployed and tested 100% 1 Done
7. Search Module Fully deployed and tested 100% 1 Done
8. Spotlight Module Fully deployed and tested 100% 1 Done
9. Calender Module (good to have) Re-picked it up but only doing a very simple setup 1 Added a very simple calender that shows events that have been paid for for day selected
10. Notification Module (good to have) Fully deployed and tested 100% 1 Done
11. Special Standalone Admin App (good to have) - - -



Moments header schedule.png



Sprint no. Planned Actual Comments
2 Account Management Part 1 11 June 2019 11 June 2019 As planned
3 Account Management Part 2 21 June 2019 21 June 2019 Completed
4 Customer Module, Vendor Module 1 July 2019 4 July 2019 Took some extra time to research
5 Customer Module, Vendor Module 11 July 2019 11 July 2019 As planned
6 Customer module, Vendor module 6 Aug 2019 6 Aug 2019 Completed
Acceptance 15 August 2019 15 August 2019 Completed Acceptance milestone
7 Booking module, Events module 17 August 2019 17 August 2019 Bookings and Events Module were added to core functions from Acceptance feedback
User Acceptance Testing 1 24 August 2019 13 September 2019 Major push back due to 2 functions (Events and Booking) being shifted to core.
8 Bookings Module, Events Module 25 August 2019 25 August 2019 As Planned
9 Bookings Module, Events Module 8 September 2019 12 September 2019 Completed
Payment Module 8 September 2019 5 September 2019 Begun early due to research time required for payment
User Testing 1 13 September 2019 13 September 2019 As planned
10 Payment 21 September 2019 21 September 2018
User Acceptance Testing 2 27 September 2018 28/29/30 September 2019 Needed a bit more time for bug fixes, as well as to gather more participants
11 Payment Module 28 September 2019 28 September 2019 Completed
Mid Term 1 October 2019 Completed
12 Spotlight Module 1 October 2019 1 October 2019 Everything went as planned
Search 1 October 2019 1 October 2019 Everything went as planned
13 Spotlight Module 15 October 2019 15 October 2019 Completed
Search 15 October 2019 15 October 2019 Everything went as planned
14 Search Module 2 November 2019 2 November 2019 Completed
User Test 3 7 November 2019 10 November 2019 Brought forward due to vendor's availability
Final Presentation 20 November 2019 20 November 2019 Ongoing
Moments header released.png
Moments releasedburndown final.jpg
Moments header velocity.png
Moments velocity final.jpg
Moments header bug.png
Moments bugspersprint final.jpg
Moments bugscore final.jpg
Moments scorebreakdown final.jpg
Moments technicalcomplexity.png


Moments Risk.png