IS480 Team wiki: 2018T2 Moments Finals
Revision as of 13:17, 20 November 2019 by Yiwen.chan.2015 (talk | contribs)
Finals Wiki
|
Stage | Specification | Modules |
---|---|---|
Project Management | Meeting Minutes | Moments Minutes |
Backlog | Moments Backlogs | |
Burndown Charts | Moments Charts | |
Diagrams | Use Case & ER Diagrams | Moments Diagrams |
Testing | UAT 2 & 3 | UT2 | UT3 |
Prototype | Paper Prototype | Moments Paper Prototype |
Presentation Slides | Final | Final Presentation |
No. | Function | Status | Confidence | Remarks |
---|---|---|---|---|
1. | Account Management Module | Fully deployed and tested 100% | 1 | Done |
2. | Vendor Module | Fully deployed and tested 100% | 1 | Done |
3. | Customer Module | Fully deployed and tested 100% | 1 | Done |
4. | Booking Module | Fully deployed and tested 100% | 1 | Done |
5. | Event Module | Fully deployed and tested 100% | 1 | Done |
6. | Payment Module | Fully deployed and tested 100% | 1 | Done |
7. | Search Module | Fully deployed and tested 100% | 1 | Done |
8. | Spotlight Module | Fully deployed and tested 100% | 1 | Done |
9. | Calender Module (good to have) | Re-picked it up but only doing a very simple setup | 1 | Added a very simple calender that shows events that have been paid for for day selected |
10. | Notification Module (good to have) | Fully deployed and tested 100% | 1 | Done |
11. | Special Standalone Admin App (good to have) | - | - | - |
Sprint no. | Planned | Actual | Comments | ||
---|---|---|---|---|---|
2 | Account Management Part 1 | 11 June 2019 | 11 June 2019 | As planned | |
3 | Account Management Part 2 | 21 June 2019 | 21 June 2019 | Completed | |
4 | Customer Module, Vendor Module | 1 July 2019 | 4 July 2019 | Took some extra time to research | |
5 | Customer Module, Vendor Module | 11 July 2019 | 11 July 2019 | As planned | |
6 | Customer module, Vendor module | 6 Aug 2019 | 6 Aug 2019 | Completed | |
Acceptance | 15 August 2019 | 15 August 2019 | Completed Acceptance milestone | ||
7 | Booking module, Events module | 17 August 2019 | 17 August 2019 | Bookings and Events Module were added to core functions from Acceptance feedback | |
User Acceptance Testing 1 | 24 August 2019 | 13 September 2019 | Major push back due to 2 functions (Events and Booking) being shifted to core. | ||
8 | Bookings Module, Events Module | 25 August 2019 | 25 August 2019 | As Planned | |
9 | Bookings Module, Events Module | 8 September 2019 | 12 September 2019 | Completed | |
Payment Module | 8 September 2019 | 5 September 2019 | Begun early due to research time required for payment | ||
User Testing 1 | 13 September 2019 | 13 September 2019 | As planned | ||
10 | Payment | 21 September 2019 | 21 September 2018 | ||
User Acceptance Testing 2 | 27 September 2018 | 28/29/30 September 2019 | Needed a bit more time for bug fixes, as well as to gather more participants | ||
11 | Payment Module | 28 September 2019 | 28 September 2019 | Completed | |
Mid Term | 1 October 2019 | Completed | |||
12 | Spotlight Module | 1 October 2019 | 1 October 2019 | Everything went as planned | |
Search | 1 October 2019 | 1 October 2019 | Everything went as planned | ||
13 | Spotlight Module | 15 October 2019 | 15 October 2019 | Completed | |
Search | 15 October 2019 | 15 October 2019 | Everything went as planned | ||
14 | Search Module | 2 November 2019 | 2 November 2019 | Completed | |
User Test 3 | 7 November 2019 | 10 November 2019 | Brought forward due to vendor's availability | ||
Final Presentation | 20 November 2019 | 20 November 2019 | Ongoing |