Line 196: Line 196:
 
| Accept
 
| Accept
 
| Completed
 
| Completed
 +
 +
|-
 +
|13
 +
|18 Jan 2018
 +
|Change in Dashboard Management Module -To indicate negative values in different colours
 +
| The change has been suggested by the client.
 +
| Team rejected the change
 +
| Low
 +
| Rejected
 +
| Not applicable
  
 
|-
 
|-

Latest revision as of 11:57, 9 February 2018

ICON Banner.jpg


Icon Home.png
Icon TheTeam.png
Icon ProjectOverview.png
Icon ProjectSchedule.png
Icon Documentation.png
PROJECT SCHEDULE TASK METRICS BUG METRICS RISK ASSESSMENT CHANGE MANAGEMENT
ICON changeManagement.PNG


Iteration Date Description Reason Feasibility Priority Accept/Reject Status
4 5 Sep 2017 Change in scope- Drop 'Invoice Management Module (2)', 'Employee Management Module' and 'Accounting Module' & Invoice Management Module (1) have been revised and combined into 'Accounting Module' After the first round of acceptance presentation and the supervisor meeting, the team has decided to revise and refine the scope for a more integrated system which has modules that are linked to one another and addresses the problem statement, creating values for the sponsor. Client agrees with the team's rationale for the change in scope and also happy to know that the team will be focusing to develop an integrated system High Accept Completed
6 9 Oct 2017 Change in the project timeline, split the accounting module task on iter 6, into two parts: 1) Map input data directly into QuickBook, 2) Map input data directly into Xero. The second part placed under tertiary function, to be done during iter 11 As the client currently utilises Quick Book more often then Xero, team proposed to focus on other core functions while delaying the connection to Xero in later iteterations. Client agrees with the team's rationale for the change in timeline. High Accept Completed
7 16 Oct 2017 Drop 'Payroll Module' from the scope. As the team aims to develop a system whereby every function/module is linked and integrated, 'Payroll Module' has been identified as independent and also creates little value for the client. Client agrees with the team's rationale for the change in scope and also happy to know that the team will be focusing to develop an integrated system High Accept Completed
7 16 Oct 2017 A project variable on the system to consists of multiple tasks Client clarified that the a project would consist of multiple tasks Team agreed to accept the additional business requirement from the client as the specification in the requirement would allow the client to better manage the project, which our project aims to achieve High Accept Completed
7 16 Oct 2017 Calendar to display tasks instead of projects With the clarification that a project would consists of multiple tasks, client suggested it would be better for the calendar to display tasks instead. Team agreed to accept the change High Accept Completed
7 18 Oct 2017 Additional User Testing added to the project timeline Having understood the important of frequent and clear communications, team suggested that additional testing and the feedback which client would offer during the testing would help the team in understanding the business requirement Client agreed with the team's reason for conducting additional testing and was happy to schedule another testing. High Accept Completed
9 13 Nov 2017 Change in the deployment date To ensure bug-free and functional system to be deployed onto the client's site, the team suggested to delay the deployment from 17 Nov to a later date. Client agreed with the team's reason for delaying the deployment date. High Accept Completed
10 2 Dec 2017 Change in Project Timeline - Expense Management Module to be completed ahead of Dashboard Module. User Testing 4,5 and 6 re-scheduled Development schedules are adjusted after re-evaluating the priorities of the modules to develop. Hence, User Testing schedules are adjusted so that each testing entails the development progress at each point. Client agreed with the team's reason for the change in schedule. High Accept Completed
12 5 Jan 2018 Change in Resource Management Module - Creating a client. Input fields for director and accountant information to be "not required" Suggested by client. Team agreed to accept the change Low Accept Completed
12 5 Jan 2018 Change in Project Management Module (3) - Creating a project. To have input field for planned hours when creating a project but when editing, only admin have the rights to. Suggested by client. Team agreed to accept the change High Accept Completed
12 5 Jan 2018 Drop Expense Management Module (2) With additional changes in the business requirements, the team and the sponsor has decided to drop the functionality to ensure that other business requirements and functionalities can be delivered on time Team agreed with the rationale to drop the functionality High Accept Completed


12 5 Jan 2018 Change in Project Management Module (1) - Create multiple ad hoc projects in a single screen. The client suggested the change for higher efficiency for their business process. As the change would require a signficant change to the current database structure, leading to further changes, the team has rejected the suggestion. Low Reject Not Applicable
12 5 Jan 2018 Change Project Management Module (1) - Project tracking calendar. External timeline to be displayed on the calendar if the internal time has passed but the project is yet to be complete. Client requested for additional measure to ensure that project/task is completed on time. While understanding that the functionality may be useful, the team reminded the client of other functionalities that are already implemented to ensure that the client meets the internal deadlines. Low Reject Not Applicable
12 5 Jan 2018 Change Project Management Module (1) - Project tracking calendar. While the calendar still shows the internal deadline for the list projects, external deadlines will also be shown together with other project details when hovered with cursor. Rejecting the earlier request from the client, the team has came up with an alternative solution. The client has accepted to implement the alternative solution Low Accept Completed
12 5 Jan 2018 Change Expense Management Module (1) - 1.Change format of current excel template to handle client request 2. Include negative expense rows 3. Added new fields 4.Increase in batch size 5. To change data for expenses inside AMS. With more employees from the client's company being involved in employees, additional feedback have been given Team agreed with the change to accommodate to the business requirements of the client. High Accept Completed
12 5 Jan 2018 Change in Dashboard Module - Split into Admin View & Employee View. Admin View includes Overall Performance, Client Performance & Employee Performance. Employee View includes Client & Employee Performance. The change was suggested by the team to further aid Abundant Accounting in reviewing the performance of the business and make necessary improvements to current pricing strategies. The client agreed with the change. High Accept Completed
13 18 Jan 2018 Change in Dashboard Management Module -To indicate negative values in different colours The change has been suggested by the client. Team rejected the change Low Rejected Not applicable
13 18 Jan 2018 Change in Project Management Module - Add a field to create and edit for client days of management account. The change has been suggested by the client. Team agreed with the change High Accept Completed