Line 143: Line 143:
 
|-
 
|-
 
| Human Risk
 
| Human Risk
| Unforeseen circumstance due to team members being unavailable as a result of emergencies or sickness.
+
| Unable to get content required from stakeholders on time.
 
| Medium
 
| Medium
 
| Medium
 
| Medium
|Ensure that every member have a copy of the latest project codes saved locally in their laptop
+
| Make do with temporary content before the actual content comes in.
 
| Yes
 
| Yes
 
|-
 
|-
| Technical Risk
+
| Human Risk
| The learning curve may be too steep for the members hence too much time taken for research purposes instead of developing the application
+
| Unable to get UT feedback on time from teachers in Myanmar
 
| Medium
 
| Medium
 
| High
 
| High
| Members will have to report the actual hours spent on learning/researching to project manager. Project manager have to decide if the task/function should be dropped or more time can be sacrificed.  
+
| Find Myanmar testers in Singapore.
 
| Yes
 
| Yes
 
|-
 
|-

Revision as of 21:55, 6 April 2017

EnglifyLogo.png

HOME

ABOUT US

PROJECT OVERVIEW

PROJECT MANAGEMENT

DOCUMENTATION

Schedule Risk Management Metrics Change Management


Risk Type Risk Event Likelihood Impact Mitigation
Technical Risk Lack of knowledge of using Android studio development for developing mobile app Medium Medium Engage developers in extensive online learning and trial and error. Have frequent review sessions on team member’s progress.
Technical Risk The learning curve may be too steep for the members hence too much time taken for research purposes instead of developing the application Medium High Members will have to report the actual hours spent on learning/researching to project manager. Project manager have to decide if the task/function should be dropped or more time can be sacrificed.
Technical Risk Not familiar with speech API and Word Search API required for speech recognition function and allowing word search via the English dictionary High High Have a thorough research done before developing functions that will use the APIs and engage experts through forums.
Technical Risk Amazon Web Services not working Low High Ensure that the application developed can do a local save to the android mobile
Technical Risk Google Services not working Low High Ensure that the application developed can do a local save to the android mobile
Technical Risk Git Lab not working Low High Ensure that every member have a copy of the latest project codes saved locally in their laptop
Client Management Risk Client might change requirements that might cause functionalities being modified. Medium High Meet and update client on a biweekly basis to ensure that the team is on track and any changes can be brought up immediately.
Human Risk Members unable to commit to the hours planned for the iteration. Low High Understand reasons for low commitment, re-schedule planned hours and manpower related to the function affected.
Human Risk Members unsatisfied with another member's work Medium Medium Ensure that the member understands his/her tasks. Have a team meeting to lay out the expectations of the work needed to be done
Human Risk Unforeseen circumstance due to team members being unavailable as a result of emergencies or sickness. Medium Medium Team member will be tasked to communicate online and keep up to date with the team on development progress. Team members are to work in pairs, therefore one may play as a backup role for the other.
Human Risk Unable to get content required from stakeholders on time. Medium Medium Make do with temporary content before the actual content comes in.
Human Risk Unable to get UT feedback on time from teachers in Myanmar Medium High Find Myanmar testers in Singapore.
Resource Risk Member's devices for development of app or required project tasks are not working Medium High Prepare a list of all applications and software that are needed for the project application development. Save a copy of all the installers for easy installation and set up. Get a spare laptop for rental and set up the development environment.
Risk Encountered


Risk Type Risk Event Likelihood Impact Mitigation Does it work?
Human Risk Members unable to commit to the hours planned for the iteration. Low High Understand reasons for low commitment, re-schedule planned hours and manpower related to the function affected. Yes
Human Risk Unable to get content required from stakeholders on time. Medium Medium Make do with temporary content before the actual content comes in. Yes
Human Risk Unable to get UT feedback on time from teachers in Myanmar Medium High Find Myanmar testers in Singapore. Yes