IS480 Team wiki: 2017T2 Bunanas Change Management
Revision as of 16:04, 1 February 2018 by Jaren.lim.2015 (talk | contribs)
Sprint | Date | Type | Change Description | Rationale | Decision | Action Taken | Status of Request |
---|---|---|---|---|---|---|---|
6 | 20 Dec 17 | Functionality | Change QR Code to Barcode | QR Code not scalable.
Barcode exists on all their inventory items. It matches all of their desired requirements. |
Change Approved | Module Changed | Closed |
6 | 24 Dec 17 | Schedule | Moving Disaster Recovery module to earlier date | Need to backup data arise during development of inventory module.
Putting disaster recovery and backup in place before further development allows for more reliable development. |
Change Approved | Project Scope & Schedule Amended | Closed |
7 | 4 Jan 18 | App Platform | Creation of Android App | Mobile-optimised web app does not work well for a barcode use case.
Not realistic to use laptop webcam during the inventorising process. Dedicated Android app will allow use of native camera functionality. |
Change Approved | Project Schedule Amended | Closed |
9 | 22 Jan 18 | Schedule | Change User Testing timeframe from standalone major milestones into multiple smaller milestones with higher frequency | The current User Testing plan worked around sponsor's process lifecycle (~2 weeks) which results in less User Testing being conducted.
Multiple activities are conducted within the lifecycle that should be tested and recorded. It was deemed to be more beneficial to have smaller tests with higher frequency to collect more data points. |
Change Approved | Discussions were made with Supervisor and Sponsor. It was decided that it would be better to have more specific names for User Tests (User Test 2: Admin, User Test 2: Beneficiary) and increase the frequency. This shows a better understanding of the stakeholders that are being addressed. | In Progress |