Bug Metrics & Mitigation Plans
Severity Description
Low Impact (Score: 1) Stable. Typo errors or small UI misalignment
High Impact (Score: 5) Application functional. Non-critical functionalities are not working.
Critical Impact (Score: 10) Stop development and fix bugs immediately
Total Score Mitigation Plans
Points < 10 Fix during buffer time only.
10 <= Points < 20 Application functional. Non-critical functionalities are not working.
Points >= 20 Stop development and fix bugs immediately
Task Metrics & Mitigation Plans


Score Action Taken
TM < 50% Inform supervisor and sponsor about delay. Re-estimate tasks with due consideration of delayed tasks.
50% < TM <= 90% Allocate incomplete tasks to buffer time. Shift back tasks if needed, and re-estimate time for subsequent tasks
90% < TM <= 110% Team estimation is fairly on track, proceed with planned schedule
100% < TM <= 150% Team is ahead of schedule. Re-estimate time for subsequent tasks as needed
TM > 150% Inform supervisor and sponsor about team being ahead of schedule. Re-estimate tasks for future iterations
Task Metrics 19Feb.png


Wellness Part 1.png
Wellness Part 2.png
WellnessMetrics.png