IS480 Team wiki: 2017T2 Bare Code Metrics
Revision as of 21:20, 4 April 2018 by Cheryl.lee.2015 (talk | contribs)
[Task Metrics ]
[| Bug Metrics]
Bug Metrics & Mitigation Plans
Severity | Description |
---|---|
Low Impact (Score: 1) | Stable. Typo errors or small UI misalignment |
High Impact (Score: 5) | Application functional. Non-critical functionalities are not working. |
Critical Impact (Score: 10) | Stop development and fix bugs immediately |
Total Score | Mitigation Plans |
---|---|
Points < 10 | Fix during buffer time only. |
10 <= Points < 20 | Application functional. Non-critical functionalities are not working. |
Points >= 20 | Stop development and fix bugs immediately |
Task Metrics & Mitigation Plans
Score | Action Taken |
---|---|
TM < 50% | Inform supervisor and sponsor about delay. Re-estimate tasks with due consideration of delayed tasks. |
50% < TM <= 90% | Allocate incomplete tasks to buffer time. Shift back tasks if needed, and re-estimate time for subsequent tasks |
90% < TM <= 110% | Team estimation is fairly on track, proceed with planned schedule |
100% < TM <= 150% | Team is ahead of schedule. Re-estimate time for subsequent tasks as needed |
TM > 150% | Inform supervisor and sponsor about team being ahead of schedule. Re-estimate tasks for future iterations |