Project Progress Summary

Our team has completed all of the core functions and 80% of the sencondary functions. We have successfully launched our app on the apple store and is ready for download. We have done 2 User Testing(UT) and a survey, we will enhance our app with user suggestions for a better quality. We are confident that we can achieve the end goal on time with the revised schedule.

Project Highlights

Positive Highlights:

  • Successfully accepted by apple store
  • Conducted 100 surveys and gather feedback for improvements.
  • Gained valuable experience learning new language - swift.

What unexpected events occurred?

  • Deployment to be brought earlier from final to mid term.

List of requirement changes:

  • To add No task taken reminder to improve business flow.
  • Changed business model from having both public and private transport deliverer to only public transport deliverer.

Project Management

Project Status

Platform Module Total Completed Remaining % Done % Total Done
IOS Account 13 11 2 84.6% 80.7%
PBT 23 19 4 82.6%
Synchronisation 11 11 0 100.0%
Notification 5 5 0 100.0%
PBT Template 5 5 0 0.0%
WEB Account 6 6 0 100.0% 55.3%
PBT Review 54 46 8 85.2%
PBT Template 22 0 0 0.0%
Analytics 12 0 0 0.0%

Project Schedule (Planned Vs. Actual)

Scope Change
Past
Current
Timeline Change
Past
Current

Project Metrics

Project Risks

Technical Complexity

S/N Complexity Rationale
1 Access Control (SSO)
2 Web Services Integration

Project Quality

Intermediate Deliverables

Topic of Interest Link
Project Management Metrics
Risk & Change Management
Project Overview Project Overview
Project Documentation Diagrams
Prototype
Testing Testing Document

Deployment:

Internal Testing

Client Testing

User Testing Date Venue Number of Testers
User Testing 1 7:00am – 2:00pm Feb 2nd 2018 ST Aerospace Academy 5
User Testing 2 3:00pm – 9:00pm Feb 10th 2018
12:00pm – 6:00pm Feb 13th 2018
ST Aerospace Academy 10

Reflection

Team Reflection


|}