Difference between revisions of "IS480 Team wiki: 2017T2 Asgardians Change Management"
Jump to navigation
Jump to search
Yfzhang.2015 (talk | contribs) |
Yfzhang.2015 (talk | contribs) |
||
Line 104: | Line 104: | ||
|style="text-align: left;"| Accept | |style="text-align: left;"| Accept | ||
|style="text-align: left;"| Front-end developer taken note and make the changes | |style="text-align: left;"| Front-end developer taken note and make the changes | ||
− | |style="text-align: left;"| | + | |style="text-align: left;"| Closed |
|- | |- | ||
Revision as of 23:16, 30 January 2018
Change Logs
Iteration | Date | Type | Change Request | Issued By | Change Description | Decision | Action Taken | Status of Request |
---|---|---|---|---|---|---|---|---|
1 | 17/10/2017 | Member | Additional join in of member | Team PM | New member of Gary to help out on the back-end developer. | Accept | PM noted and change task allocation and project schedule. | Closed |
3 | 07/11/2017 | Schedule | Date of deployment to IOS | Prof Benjamin Gan | Deployment to IOS to bring forward from final to mid term. | Accept | The team rescheduled and prosponed good to have function to after mid term and focus on main functions first. | Closed |
3 | 07/11/2017 | Front-end Design | Back ground for Main Page UI | Prof Benjamin Gan | Would like to make the back ground of the app more relavant with the business.Remove the current background. | Accept | Front-end developer taken note and make the changes | Closed |
8 | 17/01/2018 | Scopes | Sender's reminder system | Supervisor Prof Yongki Lee | To add a sender's reminder system to increase price for item that has not been picked up more than 2 hours | Accept | PM added additional function no task taken reminder in Iteration 9 | Implementing |