IS480 Team wiki: 2017T1 Team BFFs Finals
Contents
Project Progress Summary
Project Highlights
The following are the project highlights for mid terms
- Supervised the use of our web application during Singapore Weiqi Association Officially Tournaments twice (Gogo Beginner Cup on 18th October and Zong Xiang Cup on 12th November) without their systems running beside us.
- Added new functions such as Import Tournaments, Users, Players and Team Players
- Conducted Security Testing
- Conducted Stress Testing
- Achieved our X-Factor with 640 active users currently using our web application
Deliverables
deployment | poster |
---|---|
Project Challenge
With these challenges. Team BFFs came out with a web application as a solution to our client. We create online tournament website that will enable Singapore Weiqi Association to organize and run all types of tournaments through a centralized website. This will make the process of organizing and running a tournament much more efficient, less time consuming and with a more error prevention methods which equate to less human errors.
X-Factor
Project Management
Project Status
Overall Project Scope
Finals Scope Focus
Project Schedule
Project Metrics
Metrics used are shown below:
Task Metrics
Bug Metrics
Sponsor Satisfaction Metrics
Team Satisfaction Metrics
Project Risks
Our team recognized the following risk and have created the following mitigations.
S/N | Risk Event | Likelihood | Impact | Mitigation |
---|---|---|---|---|
1 | New users (especially players) do not know how to navigate the new website | Medium | Medium | Ensure that actual players attend our UATs to get usability feedback if our design is intuitive enough for new users. |
2 | Delays due to unfamiliar Weiqi match pairing logic. | High | High | Frequent checks with Sponsor to confirm if pairing logic is correct and compare pairings with past tournaments |
3 | Server crashes due to large amount of players using the system concurrently | Medium | High | Improve the efficiency of the website and upgrade the server RAM |
Technical Complexity
Quality of Product
Intermediate Deliverables
deployment | minutes | metrics | risk management | change management | project overview | diagrams | prototype | testing document |
---|---|---|---|---|---|---|---|---|
Sponsors' Evaluation
Reflections
To be updated