Project Status
Project Schedule (Plan vs. Actual)
Several changes were made to the project schedule due to greater emphasis on Data Classification module and preparation for Lab Release(Live usage) as requested by sponsors. Hence, Atoms had rescheduled and dropped afew tasks that were not critical for the lab completion (as reflected in the actual schedule). The changes in the iterations were made to ensure the completion of the project on time and to also optimize the sponsor's requirements. Progress of the team is well-paced and optimistic.
Planned Project Schedule
Actual Project Schedule
Project Metrics
Change Management
Below is the change log for Iteration 7 to 10 (after acceptance):
Iteration | Date | Type | Change Request | Rationale | Feasibility | Outcome | Priority | Status of Request | Issued By |
---|---|---|---|---|---|---|---|---|---|
7 | 19/8/2017 | Scope & Schedule | Reschedule classification and clustering module | Reschedule functions based on lab exercise and release dates | Fits into schedule without any expected delay as a consequence. | Accepted | High | Closed | Team |
8 | 23/8/2017 | Scope | Remove Neural Network function | Team feels that scope is too large and functionality is not critical for labs completion | Group, sponsor and supervisor agree to removal of unnecessary functions | Accepted | High | Closed | Team |
8 | 02/9/2017 | Scope | Add Aggregation function | Team realize that the functions is required to effectively complete Lab1 | Fits into schedule without any expected delay as a consequence | Accepted | Low | Closed | Team |
9 | 08/8/2017 | Scope | Add XG Boost(New Classification technique) function | Sponsor highlighted that this is a commonly used classification technique and will be really useful for student projects. Team has excess time to complete this | Fits into schedule without any expected delay as a consequence | Accepted | Low | Closed | Sponsor |
9 | 08/8/2017 | Scope | Add static documentation web page | Sponsor request for documentation/user guide to allow new users to be familiarize with the system. Team has excess time to complete this function | Fits into schedule without any expected delay as a consequence | Accepted | Low | Closed | Sponsor |
Project Risks
Technical Complexity
Frontend
1. Canvas Graph Traversing Algorithm
In the KDDLabs, user can draw their own data mining process in the canvas with all the legit combination of functions. When users execute the process in the canvas, they are able to choose to partially execute the process or fully execute. In order to achieve this feature, our team designed a graph traversing algorithm to handle all the possible combinations the user could draw in the canvas. The pseudo code and logical flow are as follow:
Following is an example when user is trying to execute the “Decision Tree Classifier 2”.
Only the nodes in execution list will be traversed and executed as shown below.
Backend
Quality of Product
Intermediate Deliverables
Topic of Interest | Link |
---|---|
Project Management | Project Schedule |
Minutes | |
Metrics | |
Risk Management | |
Change Management | |
Project Overview | Project Overview |
Team's Motivation | |
Project Scope | |
Project Documentation | Diagrams |
Technologies Implemented | |
Low & Mid Fidelity Prototypes | |
Testing | Testing Documentation |
Deployment
Note: Application link provided is for our test server, which is only available within the SMU Network. Otherwise consider using VPN to access the SMU Network
To view application, visit
Test server: http://10.0.106.101/
Username: demo
Password: demopassword123
Note: This public server is currently being utilized for Live Usage by the IS424 Data Mining and Business Analytics students for their labs and project completion.
Production server: https://kddlabs.cn/
Testing
Internal Testing
We engage in comprehensive manual testing in every iteration. The developers will conduct individual testing before committing their codes on our shared repository, GitHub. We believe in testing the application manually at this level because tests can be specially adjusted to cater to changes in the application, both on the front and back end. Furthermore, manual testing brings about the human factor, allowing us to better discover problems that might surface during real usage due to natural human behavior.
Once the developers have fixed the bugs, the fixed set of codes will be merged and integrated with the other functionalities. Subsequently, the integrated code is then deployed on the test server and the lead quality assurance will run a final check against the set of test cases created. This helps to ensure that the deployed application works with no major incidents.
The team's lead quality assurance then performs regression testing on the test server where previous functionalities developed are tested again. This helps to ensure that existing functionalities in the application are not affected by the integration. Once bugs have been identified, the lead quality assurance will then update the bug-tracking Excel sheet and notify the relevant developers of the issues and the corresponding priority level.
The team’s list of test cases can be found on our private repository here.
User Acceptance Test 1 & 2
Team Atoms has conducted 2 user tests which allowed us to better manage sponsor expectations as well as improve on usability of our application interface.
For more detailed version of Team Atoms user acceptance test results, access it here:
Live Usage
Through our live usage and roll out, IS424 students were able to complete their take home lab assignments on our system. Thus we were able to gather feedback from our end users about KDD Labs system directly. In addition, we were also able to compare the user experience with the existing alternative used in class (SAS EM). From our feedback, we have received positive response about the KDD Labs system stating that the students were able to complete their in class lab exercise. Not only that, they also found that the KDD Labs system was easier to use as compared to SAS EM.
Lab1
Release Date: 01 Sep 2017, Friday
Duration: 2-3 hours per user
Number of Users(s): 45
Lab1 User Guide: Created instructions can be found here
FEEDBACK RESULTS FROM LIVE USERS
Lab1 Feedback Results: The rest of the results from the Live user feedback can be found here
Lab2
Release Date: 15 Sep 2017, Friday
Duration: 2-3 hours per user
Number of Users(s): 45
Lab2 User Guide: Created instructions can be found here