Project Progress Summary
User: demo | Password: demopassword123
Project Highlights [in chronological order]
Project Management
Project Status
Project Schedule (Plan vs. Actual)
Several changes were made to the project schedule due to greater emphasis on Data Classification module and preparation for Lab Release(Live usage) as requested by sponsors. Hence, Atoms had dropped afew tasks that were not critical for the lab completion (as reflected in the actual schedule). The changes in the iterations were made to ensure the completion of the project on time and to also optimize the sponsor's requirements. Progress of the team is well-paced and optimistic.
Planned Project Schedule
Actual Project Schedule
Change Management
Below is the change log for Iteration 7 to 10 (after acceptance):
Iteration | Date | Type | Change Request | Rationale | Feasibility | Outcome | Priority | Status of Request | Issued By |
---|---|---|---|---|---|---|---|---|---|
7 | 19/8/2017 | Scope & Schedule | Reschedule classification and clustering module | Reschedule functions based on lab exercise and release dates | Fits into schedule without any expected delay as a consequence. | Accepted | High | Closed | Team |
8 | 23/8/2017 | Scope | Remove Neural Network function | Team feels that scope is too large and functionality is not critical for labs completion | Group, sponsor and supervisor agree to removal of unnecessary functions | Accepted | High | Closed | Team |
8 | 02/9/2017 | Scope | Add Aggregation function | Team realize that the functions is required to effectively complete Lab1 | Fits into schedule without any expected delay as a consequence | Accepted | Low | Closed | Team |
9 | 08/8/2017 | Scope | Add SG Boost(New Classification technique) function | Sponsor highlighted that this is a commonly used classification technique and will be really useful for student projects. Team has excess time to complete this | Fits into schedule without any expected delay as a consequence | Accepted | Low | Closed | Sponsor |
9 | 08/8/2017 | Scope | Add static documentation web page | Sponsor request for documentation/user guide to allow new users to be familiarize with the system. Team has excess time to complete this function | Fits into schedule without any expected delay as a consequence | Accepted | Low | Closed | Sponsor |