Project Progress Summary
Project Highlights:
- User Acceptance Test 3 was completed on 2 November
- Implemented Voting module (Upvote/downvote for each post) in Sprint 11 (2 Oct - 15 Oct)
- Implemented Client Reporting module for TSL Facebook, Instagram and YouTube page in Sprint 12 (16 Oct - 29 Oct)
- Implemented Telegram Bot to send daily reports containing a) new posts across Instagram, YouTube and Websites b) Top 10 Viral Posts across platforms in Sprint 12-13 (16 Oct - 12 Nov)
- Integrated Telegram Bot to send daily reports to 90 employees automatically at the end of Sprint 13
- Integrated Google Analytics to track user activities at the end of Sprint 13