Schedule & Effort Metrics


Team VI Schedule Metrics.png


Schedule Metrics
Team VI Schedule Metrics Graph.png


We are currently in Iteration 14.
Iteration Period Planned Duration (Days) Actual Duration (Days) Schedule Metric Score Actions
1
31 Aug 2015 - 06 Sep 2015
14
14
100%
On track and iteration to proceed as planned.
2
07 Sep 2015 - 20 Sep 2015
14
14
100%
On track and iteration to proceed as planned.
3
21 Sep 2015 - 04 Oct 2015
14
14
100%
On track and iteration to proceed as planned.
4
05 Oct 2015 - 18 Oct 2015
14
14
100%
On track and iteration to proceed as planned.
5
19 Oct 2015 - 05 Nov 2015
14
18
77.78%
Underestimated time required, PM to re-estimate tasks for future iterations.
6
06 Nov 2015 - 20 Nov 2015
14
14
100%
On track and iteration to proceed as planned.
7
10 Dec 2015 - 23 Dec 2015
14
14
100%
On track and iteration to proceed as planned.
8
24 Dec 2015 - 07 Jan 2016
14
14
100%
On track and iteration to proceed as planned.
9
07 Jan 2016 - 26 Jan 2016
14
20
70%
Underestimated the time required and PM to re-estimate for future iterations.
10
27 Jan 2016 - 9 Feb 2016
14
15
93.33%
On track and iteration to proceed as planned.
11
10 Feb 2016 - 24 Feb 2016
14
14
100%
On track and iteration to proceed as planned.
12
25 Feb 2016 - 09 Mar 2016
14
14
100%
On track and iteration to proceed as planned.
13
10 Mar 2016 - 24 Mar 2016
14
14
100%
On track and iteration to proceed as planned.
14
25 Mar 2016 - 06 Apr 2016
14
14
100%
On track.


Effort Metrics
Team VI Effort Metrics Graph.png


Iteration Period Planned Hours Actual Hours Effort Metric Score Status
1
31 Aug 2015 - 06 Sep 2015
84
90
93.3%
On track.
2
07 Sep 2015 - 20 Sep 2015
145
148
98%
On track.
3
21 Sep 2015 - 04 Oct 2015
160
180
88.8%
Underestimated hours required. Re-estimate tasks for future iterations
4
05 Oct 2015 - 18 Oct 2015
100
90
111%
Over-estimated hours required. Re-estimate tasks for future iterations.
5
19 Oct 2015 - 05 Nov 2015
150
180
83.3%
Underestimated hours required. Re-estimate tasks for future iterations
6
06 Nov 2015 - 20 Nov 2015
92
94
97.9%
On track and iteration to proceed as planned.
7
10 Dec 2015 - 23 Dec 2015
195
205
95%
On track and iteration to proceed as planned.
8
24 Dec 2015 - 07 Jan 2016
175
183.5
95%
On track and iteration to proceed as planned.
9
07 Jan 2016 - 26 Jan 2016
119
139
85.6%
Underestimated the time required and PM to re-estimate the time required for future iterations.
10
21 Jan 2016 - 03 Feb 2016
107
112
95.54%
On track and iteration to proceed as planned.
11
10 Feb 2016 - 24 Feb 2016
120
125
96%
On track and iteration to proceed as planned.
12
25 Feb 2016 - 09 Mar 2016
109
112
97.32%
On track and iteration to proceed as planned.
13
10 Mar 2016 - 24 Mar 2016
103
107
96.26
On track and iteration to proceed as planned.
14
25 Mar 2016 - 06 Apr 2016
118
121
97.52%
On track.