Task metrics - measure the team’s efficiency/competency in completing tasks.
Indicator of accuracy in estimating complexity of tasks.

Formula: (Planned Hours / Actual Hours) * 100
Score (%) Action
SM <= 90 The team is behind the schedule.

Under-estimated the effort required.
Re-estimate tasks for future iterations.
Deduct the number of days behind schedule from buffer days.
If there is no more buffer days left, decide to drop any functionalities.

90 < SM <= 110 Estimates are generally accurate and on track.
> 110 The team is ahead of schedule.

Over-estimated the effort required.
Re-estimate tasks for future iterations.
Add the number of days gained back to the buffer days.

Task Metrics Score (%)

View our detailed tasks here.

Team ProgneSIS Task Metrics Score Graph.png

Task (Planned vs Actual Hours)

Team ProgneSIS Task (Planned vs Actual).png

Task Metrics Summary


Iteration Planned Duration (Hours) Actual Duration (Hours) Task Metrics Score (%) Action Status
1 271.2 279.6167 96.9899 Estimates are generally accurate and on track. Completed
2 164 161 101.8634 Estimates are generally accurate and on track. Completed
3 85 87 97.7011 Estimates are generally accurate and on track. Completed
4 115.2 113 101.9469 Estimates are generally accurate and on track. Completed
5 163 150.5 108.2353 Estimates are generally accurate and on track. Completed
6 147.5 148.5 95.9596 Estimates are generally accurate and on track. Completed
7 159.5 155.5 102.5723 Estimates are generally accurate and on track. Completed
8 158 150.5 104.9834 Estimates are generally accurate and on track. Completed
9 149.5 144.5 103.4602 Estimates are generally accurate and on track. Completed
10 147 147 100 Estimates are generally accurate and on track. Completed
11 144 144 100 Estimates are generally accurate and on track. Completed
12 144 144 100 In Progress -