IS480 Team wiki: 2016T2 ProgneSIS Schedule Metrics
Jump to navigation
Jump to search
Project Schedule | Schedule Metrics | Task Metrics | Bug Metrics | Risk Management | Change Management |
|
Iteration | Planned Duration (Days) | Actual Duration (Days) | Schedule Metric Score (%) | Action | Status |
---|---|---|---|---|---|
1 | 21 | 22 | 95.2381 | Estimates are generally accurate and on track | Completed |
2 | 23 | 23 | 100 | Estimates are generally accurate and on track. | Completed |
3 | 14 | 14 | 100 | Estimates are generally accurate and on track. | Completed |
4 | 14 | 14 | 100 | Estimates are generally accurate and on track. | Completed |
5 | 14 | 14 | 100 | Estimates are generally accurate and on track. | Completed |
6 | 14 | 14 | 100 | Estimates are generally accurate and on track. | Completed |
7 | 14 | 14 | 100 | Estimates are generally accurate and on track. | Completed |
8 | 14 | 14 | 100 | Estimates are generally accurate and on track. | Completed |
9 | 14 | 15 | 93.3333 | Estimates are generally accurate and on track. | Completed |
10 | 14 | 13 | 107.6923 | Estimates are generally accurate and on track. | Completed |
11 | 14 | 14 | 100 | Estimates are generally accurate and on track. | Completed |
12 | 9 | 9 | 100 | Estimates are generally accurate and on track. | Completed |