Difference between revisions of "IS480 Team wiki: 2016T2 LickiLicky Midterm Wiki"

From IS480
Jump to navigation Jump to search
Line 59: Line 59:
 
{| class="wikitable" style="text-align:center; background: white; margin: 0px; width: 100%"
 
{| class="wikitable" style="text-align:center; background: white; margin: 0px; width: 100%"
 
! style="background: #465d66; color: white; font-weight: bold; width: 50%" | Planned
 
! style="background: #465d66; color: white; font-weight: bold; width: 50%" | Planned
 +
|-
 +
|[[File:Timeline Acceptance.PNG|500px|center|link=]]
 +
|}
 +
 +
{| class="wikitable" style="text-align:center; background: white; margin: 0px; width: 100%"
 
! style="background: #465d66; color: white; font-weight: bold; width: 50%" | Actual
 
! style="background: #465d66; color: white; font-weight: bold; width: 50%" | Actual
 
|-
 
|-
|[[File:Timeline Acceptance.PNG|500px|center|link=]]
 
 
|[[File:Timeline Midterm.V2.png|500px|center|link=]]
 
|[[File:Timeline Midterm.V2.png|500px|center|link=]]
 
|}
 
|}

Revision as of 14:00, 23 February 2016

LickiLicky Logo v2.png

HOME   ABOUT US   PROJECT OVERVIEW   PROJECT MANAGEMENT   DOCUMENTATION
Main Wiki Midterm Wiki Final Wiki


Project Progress Summary

Midterm Slides: To be uploaded

Current Iteration: 12
Total Iterations: 16
Iteration Dates: 20 February 2016 to 4 March 2016

  • Overall Project Progress: 90%
  • Modules To-Be Done - Tertiary: Backup Module (Cloud backup)
  • Modules To-Be Done - Good to Have: Smart Module (Best time to contact)
  • Modules Completed: User, Note Taking, Search, Reminder, Group, Social, Multimedia, Scheduling
  • LickiLicky is confident of completing all modules up till tertiary functions with an additional good to have function
  • Android Mobile Application to be deployed on Google Play Store

Project Highlights

  • To be updated


Project Management

Project Scope


LickiLicky_Scope_2.1

Project Timeline

Planned
Timeline Acceptance.PNG
Actual
Timeline Midterm.V2.png


Project Status

Module Status Confident Level (0-1) Comment
User 100% 1 Fully deployed and tested.
Note Taking 100% 1 Fully deployed and tested.
Search 90% 0.9 Tag Contacts in Notes and Hashtags functions to be improved.
Reminder 100% 1 Fully deployed and tested.
Group 100% 1 Fully deployed and tested.
Social 90% 0.9 Link Contacts to be improved.
Multimedia Module 90% 0.9 Attach Media to Notes to be improved.
Scheduling Module 100% 1 Fully deployed and tested.
Backup Module 50% 0.5 Cloud backup to be developed after Midterm.

View our Project Timeline Here!


Schedule Highlights The following changes has been made to our project scope and reflected in our schedule.

  • Secondary Functions – Google Analytics, Birthday Reminder, and Create Event were added to scope and scheduled to be developed on iteration 7, 8 and 10 respectively.
  • Tertiary Functions – Hashtags was shifted from secondary function. Data Migration was added to scope and scheduled to be developed on iteration 11.
  • Added in Good to Have functions. These are functions which we may consider to develop during IS480.
    • Good to Have – OTP registration and login was shifted from secondary function. Visualization of Statistics and Premium / Freemium Access Control were shifted from tertiary function. Best time to contact was added to scope and schedule to be developed on iteration 14.

Refer to our Change Management for more!

Project Metrics

Schedule Metrics

Schedule Metrics Overview.png


Iteration Planned Duration (Days) Actual Duration (Days) Schedule Metric Score Action Taken Status
3 14 16 0.88 More time needed to complete suggest group function.

Follow up action: Schedule slip was presented during Acceptance presentation. No delay to overall schedule as there are no major function to be developed in Iteration 4, which was scheduled to be preparation for Acceptance. Supervisor was informed of the slip after project was Accepted.

Completed
7 14 16 0.88 More time needed to develop filter search function.

Follow up action: Supervisor informed about delay. More hours was put into developing the function. No major delay in overall schedule as PM scheduled only one function, birthday reminder, to be developed in Iteration 8 due to festive period.

Completed
11 14 17 0.82 More time needed to develop Hashtags and debug bugs reported for User Test 3

Supervisor informed about delay. More hours was put into developing the function. No major delay in overall schedule as no major function was scheduled to be developed in Iteration 12, prior to Midterm Presentation.

Completed

View our Schedule Metrics Here!

Bug Metrics

Bug Metrics.png


Iteration Bug Score Bug Summary Action Taken
5 42
7 Low
3 High
2 Critical
A major regression testing was perform after acceptance which causes the spike in bug count. The 2 critical bugs are "new contacts added not reflected under suggest group" and "reminders and notes not backup upon app updates". Resolve bugs immediately. No major delay was caused as iteration 5 was scheduled for post acceptance debugging.
6 30
5 Low
3 High
1 Critical
1 critical bug was due to app crash when reminder was set for a non-existing group and there is a notification for this reminder. Resolve bugs immediately. No major delay was caused as iteration 6 was scheduled for post acceptance debugging.
8 10
2 High
2 high bugs were "expired reminders continue to remain in reminder list" and "recurring reminders did not take on new date/time" Resolve bugs immediately. No major delay was caused as iteration 8 was scheduled for post acceptance debugging and development of only 1 function, birthday reminder.
9 122
7 Low
11 High
6 Critical
The spike in bug count were bugs that were reported during User Test 2. The critical bugs were mainly due to app crashes after a series of actions were performed using different phone models. Resolve bugs immediately. UT2 took place over a week period and it was design to have participants to submit a daily feedback form. Participants would also report bugs to us which allows the developers to resolve the bugs on a daily basis. PM scheduled a "debugging (backlog)" task and allocated the Lead Developer to resolve these bugs while having 2 Backend Developers to develop the functions that were scheduled for Iteration 9.
10 30
4 High
1 Critical
The critical bug was an app crash while performing a series of actions using Note 3. Resolve bugs immediately. Critical bug did not occur again after new APK was released. Similar action was performed but bug did not replicate.
11 72
8 Low
3 High
1 Critical
The critical bugs were app crashed such as when user tried to upload video to his note, filter search caused app crashed searched for a wide range for age / income, and when user select the "call" option when a reminder notification was sent to the user but it was not assigned for any particular contact. Resolve bugs immediately. PM scheduled a "debugging (backlog)" task prior to UT3 and allocated the Lead Developer to resolve them while having 2 Backend Developers to develop the remaining functions. The crashes did not occur during UT3. However, UT3 participants reported several UI bugs (low) which include keyboard blocking what user is typing, "attach" icon blocking their screen.

Viewed our Bug Metrics Here!

Task Metrics

Task Metrics.png


Iteration Task Score Description Action Taken
9 0.87 Underestimated the hours needed to develop link contact (0.67) Underestimated the hours needed for debugging (0.6) Underestimated the hours needed to analyse user test result (0.5) Allocate more hours for future development tasks with similar level of complexity.

Allocate more hours to analyse user test result for future user test.

Project Risks

Risk Description Category Impact Mitigation Strategy
Team is unfamiliar with android development. Low Project may be potentially delayed due to time spent on learning. Quality of product may be affected. This risk has been lowered from High (during Acceptance stage) to Low. The developers are now more familiar with android development. However, this remain as a risk. Developers will share their knowledge with each other whenever a problem arise.
Mismatch of product against market. Medium Developed product may not be what our target users or anyone in the market wants. The risk has been lowered from High (during Acceptance stage) to Medium. More interviews have been conducted to validate market needs against project idea.
Quick rise of direct competition Medium Google can easily integrate its contacts app with notes (i.e. Google Keep), reminders (e.g. Google Tasks) and even calendars. The risk has been lowered from High (during Acceptance stage) to Medium. By targeting a niche market like FCs, and possibly patenting certain novel features of the app in the near future, we will remain competitive against bigger software companies. Furthermore, the team has enhanced knowledge about the Singapore market which also allow us to remain competitive.
Limited variety of Android phone models to perform testing Medium There may be compatibility issues with less popular Android phone models. We stretch our user testing period which will allow us to continuously recruit participants and allow testing on more variety of phones.
Risk of not having sufficient actual testers (Financial Consultant) Medium Not recruiting enough Financial Consultants to test the product may result in mismatch of product against market. The team recruited actual user during User Tests but the eventual number does not count as a sufficient sample size. PM has schedule a UAT in Iteration 14, where the product, projected to be developed up to all tertiary functions with an additional good to have function, will be tested on the real market. The team will be working closely with our mentor for this and our BA is constantly in touch with our target market.

Technical Complexity

To be Uploaded

Quality of Product

Intermediate Deliverables

Stage Specification Modules
Project Requirements Market Research Market Research
Project Management Minutes Minutes
Metrics Schedule Metrics
Task Metrics
Bug Metrics
Risk Risks
Change Management Change Management
Diagrams Class Diagram
Workflow Model
Logical Diagram
Diagrams
Design Low-Fi Prototype
High-Fi Prototype
UI Prototype
Testing User Testing 1 User Test 1
User Testing 2 User Test 2
User Testing 3 User Test 3

Deployment

User Testing

User Testing Date Venue Users Link
User Testing 1 30 Oct 2015 SMU SIS GSR2.1 2 User Testing 1
User Testing 2 6 Jan 2016 - 12 Jan 2016 On-site at SMU SIS Lift Lobby Bench and off-site 32 User Testing 1
User Testing 3 11 Feb 2016 - 16 Feb 2016 On-site at SMU SIS SR 2.1 / GSR 2.1 on 12 Feb 2016. Off-site for rest of the days 28 User Testing 1


Reflection