Difference between revisions of "IS480 Team wiki: 2016T2 Friendchise Final Wiki"
Jump to navigation
Jump to search
Translating data from servlet to PDF file Use of tokens to reset password
Line 63: | Line 63: | ||
<h2>Project Challenges</h2> | <h2>Project Challenges</h2> | ||
* | * | ||
− | + | ||
<h2>Project Achievements</h2> | <h2>Project Achievements</h2> |
Revision as of 23:20, 11 April 2016
Project Progress Summary
Final Presentation Slides:
Video Pitch:
Poster:
Project Highlights
- Successful Deployment on Google Play Store on <DATE>. Link:
- Successful Deployment of backend web admin portal on Openshift. Link:
Project Challenges
Project Achievements
Project Management
Project Scope
Project Timeline
Planned Project Schedule
Actual Project Schedule
Project Metrics
Schedule Metrics
Bug Metrics
Project Risks
Category | Description | Likelihood | Impact | Mitigation |
---|---|---|---|---|
Technology | Unfamiliar with Android mobile technology and Spring framework | High | High | Project Manager: Arrange for crash course and update team members of available online resources.
Backend Developer: Find out how much effort is needed in Android Development and advise the Project Manager in future planning of schedules. |
Team Resources | Team members may fall sick or laptops may crash | Medium | Medium | All members: Always duplicate a copy of documentation or code in dropbox, to ensure at least one working copy.
Project Manager: To keep RWS Sponsor updated regularly and ensure that frontend and backend codes are up to date. |
Client Resources | Inaccessibility of client servers | High | High | Project Manager: Tap onto school resources for the time being until client provides the green light to shift to client side server. |
Project Management | Functions might change over time as RWS might have new features to suggest | Medium | Medium | Project Manager: Adjust schedule with necessary changes whenever new functions come in. Seek opinions from team members as to whether new scope is manageable. |
Scheduling | Difficult to measure complexity of tasks and the necessary effort required | Medium | Medium | Project Manager: Conduct review of approximation via schedule metrics at end of every iteration.
|
Technical Complexity
Quality of Product
Intermediate Deliverables
Deployment
- Deployed Back-End Admin Website Link: http://rwsjobportal-pohhui.rhcloud.com/login.jsp
- Android Mobile Application Link: https://play.google.com/store/apps/details?id=rws.jobs.app.androidfive
User Testing
User Testing | Date | Venue | Users |
---|---|---|---|
System Integration Testing | 12 Feb 2016 | SMU Group Study Room | Friendchise Team |
User Testing 1 | 25 - 27 Jan 2016 | SMU Group Study Room | 18 - 25 year old individuals |
User Testing 2 | 26 - 27 Feb 2016 | SMU Group Study Room | 18 - 25 year old individuals |
Reflection
Team Reflection
- Importance of managing client expectation
- Opportunity to explore mobile application development
- Importance of adapting to changing requirements
Individual Reflection