|Before Midterms, Facebook login and Social Media was not working. All actions submitted by users were being rejected. Admin was unable to edit the news, and had to delete the news to create a new one in order to edit it. Users were unable to claims rewards even though they have enough points.
 
|Before Midterms, Facebook login and Social Media was not working. All actions submitted by users were being rejected. Admin was unable to edit the news, and had to delete the news to create a new one in order to edit it. Users were unable to claims rewards even though they have enough points.
 
|Stop current development and resolve the bug immediately. Project Manager reschedules the project.
 
|Stop current development and resolve the bug immediately. Project Manager reschedules the project.
 +
|-
 +
|7
 +
|<b>30</b> <br> 3 High 1 Critical <br>
 +
|When working on the report module, the database was not returning all the values based on the filters chosen. We were unable to generate an excel file based on the html values and we struggled with it. We were unable to extract the sum of values from the database because of how the values were stored differently. The rank, action and pledges count on the homepage was not increasing accordingly after submission.
 +
|Stop current development and resolve the bug immediately. Project Manager reschedules the project.
 +
|-
 +
|8
 +
|<b>25</b> <br> 1 High 3 Low <br>
 +
|Image upload option for pledge was not optional and users were not able to take a pledge without uploading an image. Users taking preset pledges uploaded by admin would appear as new pledges. Pledge history was supposed to show only user side pledge but the pledges uploaded by admin appears as well
 +
|Stop current development and resolve the bug immediately. Project Manager reschedules the project.
 +
|-
 +
|9
 +
|<b>1</b> <br> 1 Low <br>
 +
|We were not able to populate drop down list with data from database when working on the filter function for events.
 +
|Use debugging phase to deal with bugs.
 
|}
 
|}
  
 
<!--Content End-->
 
<!--Content End-->

Latest revision as of 17:31, 16 April 2016

EcoCo.png


Home.png   HOME

 

About Us.png   ABOUT US

 

Overview.png   PROJECT OVERVIEW

 

Project Management.png   PROJECT MANAGEMENT

 

EcoCo Documentation.png   DOCUMENTATION

 

 Project Schedule    Risk Metrics    Schedule Metrics    Bug Metrics    Change Management 


Bug Metrics 6 11 2015.png
Bug Metrics
Bugsgraph.PNG
Iteration Bug Score Summary of bugs Action Taken
1 10
2 High
Facebook login not working. Instagram posts with the right hashtags were not being grabbed. Stop current development and resolve the bug immediately. Project Manager reschedules the project.
2 21
1 Low 4 High
Eco Actions submitted were not being stored in the database. Not all past Eco Actions were able to be displayed in the history. No deduction of points after Redeeming Reward. Stop current development and resolve the bug immediately. Project Manager reschedules the project.
3 28
3 Low 3 High 1 Critical
Edit button for Events and News were not working. Events added by Admin were not being added into the database. Stop current development and resolve the bug immediately. Project Manager reschedules the project.
4 42
2 Low 2 High 3 Critical
While improving on the UI after the functionalities have been completed, the entire web application stopped working and all pages gave us a PHP error. View Eco Actions only displayed a maximum of one action. User's reward claims not being processed in the database. Stop current development and resolve the bug immediately. Project Manager reschedules the project.
5 6
1 Low 1 High
For statistics, the amount saved were being added into the wrong categories. Rewards being added are misaligned when displayed. Use debugging phase to deal with bugs.
6 25
3 High 1 Critical
Before Midterms, Facebook login and Social Media was not working. All actions submitted by users were being rejected. Admin was unable to edit the news, and had to delete the news to create a new one in order to edit it. Users were unable to claims rewards even though they have enough points. Stop current development and resolve the bug immediately. Project Manager reschedules the project.
7 30
3 High 1 Critical
When working on the report module, the database was not returning all the values based on the filters chosen. We were unable to generate an excel file based on the html values and we struggled with it. We were unable to extract the sum of values from the database because of how the values were stored differently. The rank, action and pledges count on the homepage was not increasing accordingly after submission. Stop current development and resolve the bug immediately. Project Manager reschedules the project.
8 25
1 High 3 Low
Image upload option for pledge was not optional and users were not able to take a pledge without uploading an image. Users taking preset pledges uploaded by admin would appear as new pledges. Pledge history was supposed to show only user side pledge but the pledges uploaded by admin appears as well Stop current development and resolve the bug immediately. Project Manager reschedules the project.
9 1
1 Low
We were not able to populate drop down list with data from database when working on the filter function for events. Use debugging phase to deal with bugs.