Project Progress
Project Highlights
Our project schedule is divided into 10 iterations
- Till date, we have completed about 80% of our development progress.
- One Soft Launch with Beta Version on 2 February 2016 with Students from Balestier Hill Secondary (before midterms)
- Two user testing with actual users (before midterms)
- Current iteration: 5
- Iteration 5: 06 February 2016 - 26 February 2016
Development Progress
Status: 80%
- The team is confident of completing the project and delivering the application on time.
Project Management
Project Scope
Planned | Now |
---|---|
Quality of Product
Reflection
Project Schedule
Metrics
Project Risks
Schedule Metrics