IS480 Team wiki: 2016T2 Codex Risk Management
Revision as of 22:22, 31 October 2015 by Yujie.xing.2013 (talk | contribs)
# | Risk Type | Risk Event | Likelihood | Impact | Category | Mitigation |
---|---|---|---|---|---|---|
1 | Technical Risk | Overall, the team is not familiar with the technologies/resources used for developing the project (i.e. PHP.) | High | High | A | We will conduct peer teaching and sharing to help each other. |
2 | Project Management Risk | Team’s lack of experience might cause delays in the iterations due to underestimate or overestimate of a programming task. | Medium | High | A | Regular meetings to update on progress. If necessary, we will re-plan task(s) for the next iteration. |
3 | Client Management Risk | Client has not fully decided upon the range of functions in her application as she is new to a e-commerce web application; may eventually lead to big scope changes. | Medium | Medium | B | Regular meet up with our client to update her on our current progress and ask for incremental feedbacks. |
4 | Client Management Risk | Client has not host an e-commerce or a website before and is not IT savy, she may experience some difficulty with using our system. | Medium | Medium | B | We try to maintain simplicity in our design but we might compile a user guide for her future reference. |
9 | Resource Risk | Unforeseeable problems with technology that could cause loss of data. | Low | High | B | Make sure that files are always updated in the dropbox, such that the loss of a local hard drive will not affect the project greatly. |
10 | Human Risk | Team members become unavailable due to sickness or other unavoidable circumstances, as we have only 4 members. | Low | Medium | C | Code sharing session, so another coder can take over the coding task from the sick member. |