IS480 Team wiki: 2016T1 Stark Mid Term Wiki
Project Progress Summary
Midterm Slides:
Current Iteration: 12
Total Iterations: 16
Iteration Dates: 26 Sep 2016 - 9 Oct 2016
- Overall Project Progress: 85%
- Modules To-Be Done - Good-To-Have feature: Dispute System & Manage Dispute (Admin): 3-way chat
- Modules To-Be Done - Good-To-Have feature: Listing: Export to forum/share on social media
- Modules To-Be Done - Good-To-Have feature: Chat: Location Check-In
- Modules To-Be Done - Good-To-Have feature: Payment: iBanking
- Modules Completed: Accounts, Review/Rating, View Pending Checkout (Admin). Payment (Credit Card)
- Team Stark is confident of completing all modules up till tertiary functions with an additional good to have function
- Web application fully deployed
Project Highlights
Project Management
Project Scope
Planned |
---|
Actual |
---|
Project Timeline
Planned |
---|
Actual |
---|
Project Status
Module | Status | Confident Level (0-1) | Comment |
---|---|---|---|
Account | 100% | 1 | Fully deployed and tested. |
Listing | 100% | 1 | "Exporting to external media" is scheduled to be completed by iteration 12 |
Chat | 100% | 1 | "Location Check-in" is scheduled to be completed by iteration 13 |
Review/Rating | 100% | 1 | Fully deployed and tested. |
Dispute System | 100% | 1 | "3-way chat" is scheduled to be completed by iteration 12 |
Manage Dispute (Admin) | 100% | 1 | "3-way chat" is scheduled to be completed by iteration 12 |
Manage Data (Admin) | 100% | 1 | Fully deployed and tested. |
View Pending Checkout (Admin) | 100% | 1 | Fully deployed and tested. |
Payment (Credit Card) | 100% | 1 | Fully deployed and tested. |
Payment (iBanking) | 90% | 0.9 | The possible lack of notification service provided by bank and thus a lack of automated system. |
View our Project Timeline Here!
Schedule Highlights
The following changes has been made to our project scope and reflected in our schedule.
- "3 way chat" was shifted from iteration 9 to iteration 12.
- "Location Check In" was added into iteration 13.
- UT3 was rescheduled from 14 Oct to 24 Oct.
- Added in Good to Have functions. These are functions which we may consider to develop during IS480.
- Good to Have - "3 way chat" was shifted from secondary function. "Location Check In" feature was added to scope.
Refer to our Change Management for more!
Project Metrics
Schedule Metrics
Iteration | Planned Duration (Days) | Actual Duration (Days) | Schedule Metric Score | Action Taken | Status |
---|---|---|---|---|---|
8 | 14 | 16 | 0.88 | More time needed to fix bugs from UT1 and after the integration of Dispute Management.
Follow up action: Informed supervisor and mentor about the delay. More hours put in for debugging. No major delay to overall schedule. |
Completed |
View our Schedule Metrics Here!
Bug Metrics
Iteration | Bug Score | Bug Summary | Action Taken |
---|
Project Risks
Risk Description | Category | Impact | Mitigation Strategy |
---|
Technical Complexity
Quality of Product
Intermediate Deliverables
Stage | Specification | Modules |
---|---|---|
Project Requirements | Market Research | Market Research |
Project Management | Minutes | Minutes |
Metrics | Schedule Metrics Bug Metrics | |
Risk | Risks | |
Change Management | Change Management | |
Diagrams | Use Diagrams Architecture Diagram |
Diagrams |
Design | Low-Fi Prototype High-Fi Prototype |
UI Prototype |
Testing | User Testing 1 | User Test 1 User Test 2 |
Deployment
- MaiMai is deployed and available at http://uat.maitwo.com
- Learn more about us at http://www.maitwo.com.
User Testing
User Testing | Date | Venue | Users | Link |
---|---|---|---|---|
User Testing 1 | 1st August 2016 - 8th August 2016 | Off-Site (At respective members' discretion) | 22 | User Testing 1 |
User Testing 2 | 12th September 2016 - 26th September 2016 | SIS GSR 2-7 & Off-Site (At respective members' discretion) | tbc | User Testing 2 |
Reflection
Team Reflection It has been a tough but great learning journey for Team STARK. We learnt to complement each others' strength and weaknesses which thus helps to provide quality work. As a self-proposed project, we felt that the most challenging aspect is that we do not have a sponsor to provide us a specific project scope. Therefore, we have to take full ownership for both business and functional requirements. We learnt that apart from focusing on development of application, market research plays a very important role in ensuring that the final product is well-needed in the real world.
Individual Reflection