Project Progress Summary


IPMAN Dashboard Final.png


IPMAN FinalsSlides Icon.png IPMAN MidTermDeployedSite Icon.png IPMAN Finals Pitch Video Icon.png IPMAN Poster Icon.png

Note: We have deployed live on Hook Coffee's existing application. However, as Team IPMAN has signed an NDA with Hook Coffee, the above link to the deployed site is only available to existing administrators in Hook Coffee. To view the application, we have created a staging server in which the credentials are available in the deployment section below.


Project Highlights


Project Challenges


Project Achievements


Project Management


Project Status

IPMAN Progress Overview Final.png


Project Schedule (Plan vs. Actual)

No major changes were made to the project schedule since the team's mid-term presentation. Firstly, the team shifted our user testing 3 from 18 October 2016 to 3 November 2016. The team settled on this decision as we wanted to ensure that all functions of our platform would be covered and tested. As such, it was pushed forward from Sprint 11 to 12 when all functions would have been completed. Next, our sponsor highlighted a prominent change that they have implemented at the start of Sprint 13. After assessing the progress and workload of the team, we were confident that integrating that feature would not set us back in any way as it meant the use of buffer time that was allocated for the sprint. Lastly, the team scheduled a project handover procedure task to ensure that there would be a proper handover timeline that the team would adhere closely to. We believe proper documentation and instructions is vital for our sponsors and their freelance developers now and in the future.

Planned Project Schedule

IPMAN Timeline MidTerm Planned.png


Actual Project Schedule

IPMAN Timeline Final Actual.png


Project Metrics


Project Risks


Technical Complexity




Quality of Product


Project Deliverables


Quality


Deployment


Testing



Reflection

Team Reflection


Individual Reflection


Sponsors' Testimonial



Silhouettes wiki background IPMAN.png