IS480 Team wiki: 2016T1 GeneSIS Final
Midterm | Final |
Project Progress Summary
Final Slides | VMIS - test ver. | Poster | Pitch Video |
Project Progress
- Current sprint: Sprint 12
- Sprint period: 17 Nov - 30 Nov
- Major milestone: Final Presentation
Project Highlights
Project Challenges
List challenging modules and their problems
Project Achievements
What is our achievement?
Project Management
Project Status
What have we promised our sponsor? Delivery status?
Midterm vs Final Scope
midterm scope here || Final scope hereMidterm | Final |
---|
scope description, what we have achieved, exactly as promised? dropped modules? changes made? sponsor happy or not
See our Project Scope page for more details on previous changes
Midterm vs Final Project Schedule
midterm schedule
final schedule
description of midterm and final schedule. differences, notable changes.
Project Metrics
Team Velocity
Formula: Average of accepted stories points of _ sprints
sprint velocity chart here
Explanation:
explanation for sprint
Sprint Burndown
Formula:
- Planned: Total planned story points over number of days in a sprint
- Actual: Actual story points completed each day in a sprint
Burndown charts from some sprints since Midterm are highlighted here.
See our Midterm Wiki page for more details on sprints prior to Midterm.
burndown sprint 9
Explanation: explanation here
burndown sprint 10
Explanation: explanation here
Risk Management
Risk Type | Risk Event | Likelihood | Impact | Mitigation |
---|---|---|---|---|
- | - | - | - | - |
Explanation: -
See our Risks page for the full list of potential risks
Unaccepted Stories of Each Sprint
<insert picture to describe what happens each sprint>
Explanation: what happens when stories are not accepted? See our Stories page for each sprint's user stories.
Technical Complexity
1. Complexity 1
description here
2. Complexity 2
description here
Quality of Project
Project Deliverables
Stage | Specification | Modules |
Project Management | Meeting Minutes | Internal, Supervisor & Sponsor Meeting Minutes |
Project Schedule | Project Schedule | |
Metrics | Project Metrics | |
Risk Management | Risk Management | |
Requirements | Project Scope | Project Scope |
User Stories | User Stories | |
Analysis | Market Research | Market Research |
Architectural Design | Architectural Design | |
Design | Prototypes | Mid & High Fidelity Prototypes |
Testing | User Test Plan & Results | User Test Plan & Results |
Project Handover | Introduction Slides | Delivered via private folder on Google Drive |
User Manual | [<we shld do a user manual> User Manual] | |
Source Code | Delivered via private folder on Google Drive |
Quality
Performance: describe how we optimize performance
Maintainability: how is our product going to be maintained?
Usability:describe how we ensured our application suited the needs of our client
Deployment
Deployed site: deployed site
Testing
User Testing 1
Venue: Vimbox Office @ Tradehub 21
Date: 11 Aug 2016, Thursday
Time: 10:00am
Duration: ~35 minutes
Number of Participant(s): 4
User Test: Instuction here
User Test Results: Click here to view
User Testing 2
Venue: Vimbox Office @ Tradehub 21
Date: 21 Sep 2016, Wednesday
Time: 6:30pm
Duration: ~45 minutes
Number of Participant(s): 5
User Test: Instruction here
User Test Results: Click here to view
User Test 3
Venue:
Date:
Time:
Duration:
Number of Participants:
User Test:
User Test Results:
UI Fixes based on User Test 3
Reflection
Team Reflection
team reflection
Supervisor Testimonial
Professor Tang Qian:
Prof Tang's Photo
Her testimonial
Sponsor Testimonial
product owner's testimonial
Individual Reflection
Khairul:
Pamela:
Yu Sheng:
Xue Ning:
Qing Wan: