IS480 Team wiki: 2016T1 Charlies-Angels-Project-Management
Revision as of 21:23, 8 November 2016 by Xwzheng.2014 (talk | contribs)
Project Schedule | Risk Management | Change Management | Metrics |
Changes in Schedule | |||
---|---|---|---|
Iteration No. | Date of Schedule Revision | Reason | Dates Changed |
3 | 1 Jul 2016 | Client requested to add Dashboard, iStockTrade, and iStockWatchList feature as it is critical for an investment portfolio management application. | Adjusted to now have 11 iterations instead of the original 9. |
4 | 10 Jul 2016 | Client requested to add a Dashboard and iStockTrade as it is critical for an investment portfolio management application. | Adjusted Iteration 4's ending date to the 29th July, Iteration 5 to begin on 30th July, and UAT has been set on 5th Aug. |
6 | 22 Aug 2016 | Client has requested for more information to be displayed on the Dashboard and RobotAdvisor, requiring us to place these features on top priority for changes. Hence, a schedule change is necessary. | Adjusted Iteration 6's ending date to 30th Aug, and adjusted all subsequent dates accordingly to accommodate for the newly proposed scope. |
7 | 12 Sep 2016 | Client has requested for this new feature as he finds it useful for the user, this requires us to place these features on top priority for changes. However, upon negotiation, there is no changes to the schedule. Instead, a swap of scope has been adopted. | Swap out the feature of StockBookCorpAction and be replaced by StockBook CDP Import feature. |