Difference between revisions of "IS480 Team wiki: 2015T6 6nificance Midterm Wiki"
Sanjayn.2013 (talk | contribs) |
Sanjayn.2013 (talk | contribs) |
||
Line 87: | Line 87: | ||
|| Design | || Design | ||
− | || | + | || 100% |
|| 1 | || 1 | ||
− | || | + | || Fully deployed and tested 100%. Sponsor approved |
|- | |- | ||
|| Photo | || Photo | ||
− | || | + | || 100% |
|| 1 | || 1 | ||
− | || | + | || Fully deployed and tested 100%. Sponsor approved |
|- | |- | ||
|| Concierge | || Concierge | ||
− | || | + | || 100% |
|| 1 | || 1 | ||
− | || | + | || Fully deployed and tested 100%. Sponsor approved |
|- | |- | ||
|| Collection | || Collection | ||
− | || | + | || 100% |
|| 1 | || 1 | ||
− | || | + | || Fully deployed and tested 100%. Sponsor approved |
|- | |- | ||
|| Social | || Social | ||
− | || | + | || 90% |
− | || 0. | + | || 0.9 |
− | || | + | || Fully deployed and tested 100%. Optimizing to be done in iteration 11 |
|- | |- | ||
− | || | + | || Analytics |
|| 0% | || 0% | ||
|| 0.8 | || 0.8 |
Revision as of 16:18, 4 October 2015
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Main Wiki | Midterm Wiki | Final Wiki |
---|
Project Progress Summary
Current Iteration : 8
Iteration Dates : 2nd Oct 2015 - 8th Oct 2015
- Modules To-Be Done: Recommendation
- Modules In-Progress: User, Social
- Modules Completed: Design, Photo, Concierge, Collection
- Overall Project Progress : 60%
- Team is therefore confident of completing the project and delivering the application on time
- Android Mobile Application to be deployed on Google Play Store on 5th Oct 2015
- Back-End Website has been successfully deployed on Google App Engine
- Back-End Website Link: http://1-dot-naildeckadminportal-1042.appspot.com/
Project Highlights:
- Sponsor not confident of producing nail polishes within project timeline due to difficulties with sourcing good quality materials
- After selecting a desired color, users now can instead can pre-order nail polish from sponsor and receive it once sponsor is ready to deliver
- Team proposed that application will become more focused on social media module in order to encourage active usage and preorders which sponsor agreed and accepted
- Team has decided to expand on the social module to provide recommendations and provide metrics for sponsor
- Team has decided to revamp the whole UI of application to make the application look more social media centric. These changes were done in iterations 6 and 7
- Removal of navigation drawer
- Interlinked rest of application features with social module
- Created new high-fi prototypes
- Heuristic evaluation done before actual coding for revamp
Project Management
Project Timeline
Planned | Actual |
---|---|
Project Status:
Module | Status | Confident Level (0-1) | Comment |
User | 75% | 1 | 2 remaining tasks to be completed after midterms |
Design | 100% | 1 | Fully deployed and tested 100%. Sponsor approved |
Photo | 100% | 1 | Fully deployed and tested 100%. Sponsor approved |
Concierge | 100% | 1 | Fully deployed and tested 100%. Sponsor approved |
Collection | 100% | 1 | Fully deployed and tested 100%. Sponsor approved |
Social | 90% | 0.9 | Fully deployed and tested 100%. Optimizing to be done in iteration 11 |
Analytics | 0% | 0.8 | Function to be done after midterms |
View Our Module Descriptions Here!
Schedule Highlights
- Three more tasks such as nail polish recommendations, algorithm to sort social media content and track top posts added in recommendations module
- User Testing 2 scheduled to be on 2nd Oct
- Deployment to Play Store on 5th Oct
- Iteration 9 scheduled to start on 9th Oct instead on 12th Oct due to removal of buffer days due to delay in previous iterations
Project Metrics:
Schedule Metrics
View our Schedule Metrics Here!
Schedule Metrics Highlights
Iteration | Planned Duration (Days) | Actual Duration (Days) | Schedule Metric Score | Action | Status |
---|---|---|---|---|---|
5 | 14 | 16 | 0.88 | More time needed to complete Update Profile function due to difficulties with uploading images to cloud database Follow up action : Informed supervisor about delay. Re-scheduled the dates and tasks of iteration 6. Reduced duration of iteration 6 from 14 days to 12 days. More coding hours per day were allocated in iteration 6 |
Completed |
6 | 12 | 14 | 0.86 | More time needed to research and complete Social Module due to complexity with creating a new social media platform from scratch Follow up action : Informed supervisor about delay. Re-scheduled the dates and tasks of iteration 7. Removed 2 buffer days in iteration 8 |
Completed |
7 | 14 | 16 | 0.88 | More time needed to debug bugs found in newsfeed and view color hashtag of social module and view user profile of user module Follow up action : Informed supervisor about delay. Reduced duration of iteration 8 from 9 days to 7 days |
Completed |
Bug Metrics
Bug Score
Bug Distribution based on Severity
Iteration | Bug Score | Bug Summary | Action Taken |
---|---|---|---|
5 | 17 3 High 2 Low |
3 high bugs were due to profile picture not being shown due to problems with uploading images to Cloud Database | Resolve bugs immediately. End date of Iteration 5 is delayed. PM to reschedule end dates and tasks of iteration 6 |
6 | 21 1 Critical 2 High 1 Low |
1 critical bug was due to app cash when newsfeed refresh is attempted without internet connection. 2 high bugs were due to number of likes and color hashtags not being accurately recorded in database | Resolve bugs immediately. End date of Iteration 6 is delayed. PM to reschedule end dates and tasks of iteration 7 |
7 | 29 5 High 4 Low |
5 high bugs were due to wrong user profile picture being displayed in the newsfeed,incorrect number of posts sometimes being displayed on user profile and incorrect color tags shown in each post | Resolve bugs immediately. End date of Iteration 7 is delayed. PM to reschedule end dates and tasks of iteration 8 |
Project Risks:
Technical Complexity:
Describe and list the technical complexity of your project in order of highest complexity first. For example, deploying on iPhone using Objective-C, customizing Drupal with own database, quick search for shortest flight path, database structure, etc.
Quality of product
Intermediate Deliverables:
Stage | Specification | Modules |
Project Requirements | Market Research | Market Research |
Project Management | Minutes | Minutes |
Metrics | Schedule Metrics | |
Metrics | Task Metrics | |
Metrics | Bug Metrics | |
Risk | Risks | |
Change | Change Management | |
Analysis | Use Case | Use Case |
System Sequence Diagram | System Sequence Diagram | |
Architecture Diagram | Architecture Diagram | |
Design | Low-Fi Prototype | UI Prototype |
High-Fi Prototype | UI Prototype | |
Testing | User test plan | User Test 1 |
Issues and changes made | User Test 1 | |
Heuristic results | Heuristic Evaluation |
Deployment:
Deployed Back-End Admin Website Link : http://1-dot-naildeckadminportal-1042.appspot.com/
Android mobile application to be deployed on Google Play Store on 5th October
Testing
We have conducted User Testing 1, Heuristic Evaluation and will conduct User Testing 2 on 2nd October.
User Testing 1
- Date: 08 August 2015
- Venue: Based on testers' convenience
- 14 Female age 14-24 years old
- 2 Male age 14-24 years old
View our User Test 1 documentation here!
Heuristic Evaluation
- Date: 12th September 2015
- Venue: SMU
- 4 SMU female students
View our Heuristic Evaluation documentation here!
Reflection
In this section, describe what have the team learn? Be brief. Sometimes, the client writes a report to feedback on the system; this sponsor report can be included or linked from here.
Team Reflection:
- Deeper insights into the world of colors
- Gained real-life experience of doing an industry-level project
- Experience in mobile application development and Google Services