Project Progress Summary
Current Iteration: 6 (02/Feb/2015 - 22/Feb/2015)
- Till date of 25/Feb/2015, we have completed 60% of our project
- Next Iteration starts on 26/Feb/2015 and ends on 08/March/2015
- Release and Deployment of our web application using MyHosting service
Project Highlights
- Completed User Acceptance Testing with 3 experienced personnel with expertise in project managing
- A feature might be dropped
- 1 feature added to scope
- Steep learning curve for back-end technologies
- Steep learning curve for project management - Gantt Chart, Burn-down Chart
- Change in Excel File for uploading - changes the structure of database
Milestones Completed
- Proposal Submission
- Project Acceptance
- User Acceptance Test 1
Milestones Remaining
- User Acceptance Test 2
- Poster Submission
- Final Presentation
- Poster Day
Project Management
Project Status
Module | Functionality | Status | Confidence Level (0-1) |
Comment |
User Account Management (Core Function) |
Login | Fully implemented and deployed. User tested in UT1 |
1 | - |
Logout | Fully implemented and deployed. User tested in UT1 |
1 | - | |
Forget Password | Fully implemented and deployed. Not tested |
1 | Able to send email for new password | |
Chart Management (Core Function) |
Gantt Chart | Partially implemented and deployed. User tested in UT1 |
0.8 | Need to perform minor changes to predecessor links & need to get user feedback to ensure chart is accurate |
Burn-down Chart | Partially implemented and deployed. User tested in UT1 |
0.7 | Need users validation of values | |
Upload/Download Project Plan | Partially implemented and deployed. User tested in UT1 & UT2 |
0.8 | A lot of validations required. Users want to add in more data | |
Project Management (Core Function) |
CRUD Project | Fully implemented and deployed. |
1 | Users only tested view & create project but not edit and delete |
Milestones | Fully implemented and deployed. User tested in UT1 & UT2 |
1 | Sara owner of function | |
Thermometer Chart (% complete) | Fully implemented and deployed. User tested in UT1 |
1 | Sara owner of function | |
Product Group Management (Core Function) |
CRUD Project Group | Fully implemented and deployed. User tested in UT1 |
1 | Louise owner of function |
Access Control for Project Group | To be developed in Iteration 7 | 0.5 | Sara and Louise will work on this | |
Risk Management (Core Function) |
CRUD Risk | Fully implemented and deployed. User tested in UT1 |
1 | Hanwen owner of function |
Viewing of issues and risks in dashboard |
Fully implemented and deployed. |
1 | User did not test this feature , only static values was shown | |
Administration Management (Secondary Function) |
CRUD User Accounts | To be developed in Tteration 7 |
1 | Admin is only able to create user accounts |
Access Control for Users | To be developed in Iteration 7 | 0.6 | Sara and Louise will work on this | |
Product Task Management (Secondary Function) |
CRUD Task | To be developed in Iteration 7 | 0.6 | This feature might be dropped |
Project Plan Update Management (Secondary Function) |
CRUD Tasks Updates (excel file) | To be developed in Iteration 7 | 0.8 | - |
Notification Management (Tertiary Function) |
Send Email for Forget Password | To be developed in Iteration 8 | 0.8 | - |
Planned Schedule Vs Actual Schedule
Iteration | Planned | Actual | Comments |
4 | 5 Jan - 18 Jan | 5 Jan - 21 Jan | Some features took longer to complete, such as burn down chart. The concept of burn down chart was slightly harder to grasp. Also, some team members were struggling with using Ajax with Yii Framework because members are also new to the framework. |
5 | 19 Jan - 1 Feb | 21 Jan - 30 Jan | Iteration 5 ended earlier because there was an issue , team was not able to deploy codes onto sponsor's server. To know more, look at risk section. |
6 | 2 Feb - 22 Feb | 2 Feb - 22 Feb | Moved functionalities to Iteration 7. Decided to fully focus on core functionality for the Iteration to ensure full validation from sponsor. Hence, secondary functionality is to be done next Iteration |
7 | 26 Feb - 8 Mar | 26 Feb - 8 Mar | Change in tasks. Tasks carried forward from Iteration 6 to Iteration 7 |
Midterms Presentation | 24 Feb | 25 Feb | Midterms presentation schedule changed twice. From 24/02 to 17/02 to 25/02 |
Change Management (optional)
Man Hours Calculation
Iteration | Comments |
3 | Exam period and 4/5 members went for TSM trip, therefore hours are low. |
4 | Team members had trouble with the framework, hence functionalities were scheduled with more hours for subsequent Iterations |
6 | Iteration 6 has a significant increase in man hours due to UAT and the preparation for the mid terms. |
Iteration | Comments |
1 | Non-Coding: Doing lots of research on framework, on charts, etc. |
6 | Coding: Pre-UAT & Post-UAT, standardization in UI. Non-Coding: Preparation of UAT materials, collating UAT results, |
Iteration | Comments |
1 | Kick started the project a little late. Rushed for FYP project acceptance. |
3 | Exam period, and 4/5 of the team went for TSM |
6 | As a UI designer, Louise wanted to standardize all the view pages before UAT, so she has to wait for main functions to be done. We wanted equal learning opportunities, so our lead developer, The PM, Tricia, focused mainly on mid terms content and scheduling
|
Changes in Scope
Project Metrics
Schedule Metrics
Schedule index that are within the green bar are in the safe zone.
Iteration | Status | Explanation |
4 | Underestimated | Start of school and timetables of members were not confirmed which made it hard for PM to schedule, and also members were adjusting to school timings after the long break |
5 | Overestimated | Team encountered a risk which turned into an issue. The task - Integrate Codes to Server, was not carried out as sponsor did not reply promptly to the request of configuration details to the server. Hence Iteration was ended earlier. |
Bug Metrics
Still calculating !!!
Project Risks
Top 3 Risks
Risk | Likelihood | Impact | Level | Mitigation | Ongoing Risk? |
---|---|---|---|---|---|
Team Members New to Yii Framework | High | Medium | A | Schedule more working hours for each functionality to ensure that there is time to do research on the framework |
Yes |
Chinese New Year Period | Medium | Medium | B | Team members will be celebrating CNY, and might not follow closely to the iteration schedule. PM will give team members more days to complete the function to ensure functionality delivered within iteration. |
Yes |
MyHosting DB Change Host Name | High | Low | B | Request for a change of host name from client or temporarily host using another server |
Yes |
Technical Complexity
- Yii PHP Framework
- The way of constructing the coding language is totally different from purely using PHP
- Gantt Chart
- Burn Down Chart
Non-Technical Complexity
The non-technical complexity involves the complexity of the project based on its business process and project management understanding.
- Microsoft Project
- This tool may seem simple to use, but in fact it is very tedious.
- Steep learning curve for first time users
- Gantt chart
- Predecessors not only contains integers, but alphabets (extracted from MS Project). One has to be familiar with MS Project to be able to understand the usage of those alphabets
- SS: Start-Start
- SF: Start-Finish
- FF: Finish-Finish
- FS: Finish-Start
- Predecessors not only contains integers, but alphabets (extracted from MS Project). One has to be familiar with MS Project to be able to understand the usage of those alphabets
- Burn down chart
- This chart requires a lot of mathematical formulas. If a wrong variable is used for calculation, it is not possible to get the correct results.
- Calculations:
- Planned Value: Planned hours / date
- Earned Value: Planned hours / date * % work completed (100% or 0%)
- Actual Value: Scheduled work hours * % work completed (100% or 0%)
Quality of Product
Intermediate Deliverables
Stage | Specification | Links |
Project Management | Meeting Minutes | The Ikan Bilis Meeting Minutes |
Schedule Metrics | The Ikan Bilis Schedule Metrics | |
Bug Metrics | The Ikan Bilis Bug Metrics | |
Requirements | Motivation Video | test |
Analysis | Use Case | The Ikan Bilis Use Case Diagram |
Architecture Diagram | ||
Functionality Diagram | ||
Design | UI Prototype | The Ikan Bilis UI Design |
Testing | User test plan | Testing |
Deployment
User Testing
Reflection
Team:
- Learnt about project management
- Learnt how to manage change specified by client
- Learnt how to manage other projects together with FYP
- Learnt about the important of team communication
- Learnt new technologies and framework
Chester Cheong:
- Learnt about technicality issues
- Learnt about resource allocation (burn down chart)
Lin Hanwen:
- Learnt about the importance of quality in a system
- Learnt how to be meticulous to draft out test cases for all possible scenarios
- Learnt how to conduct a user acceptance testing
- Learnt how to manage clients as a Business Analyst
- Learnt how to understand the needs of a user
Louise Teng:
- Learnt more about UI designing
- Learnt about the importance of intuitiveness in a user interface
Sara Chan:
- Learnt about managing developers as a lead developer
- Learnt more about the setting up of a base for the system
Tricia Teo:
- Learnt about project managing
- Learnt about being more meticulous in planning and scheduling
- Learnt to be more forward-looking to anticipate future risks
- Learnt to be agile in adapting to changes and risks that has occured
- Learnt to be appropriately pessimistic when planning a schedule